Indian Boiler Regulations, 2026 · Chapter 12 · Shell Type Boilers of Welded Construction

Regulation 502. Pads welded to shell or the attachment of flanged mountings

Official text — not yet verifiedGazette 1 Oct 2026 · printed pp. 796–797TableFormula / symbols

Not yet checked against the official Gazette; verify before relying on it.

Reproduced from the Gazette of India · verification status above

502.Pads welded to shell or the attachment of flanged mountings.─ The size of outer peripheral fillet welds by which circular pads are attached to shell plates shall be determined by the Equation (12/37), but shall in no case be less than the inner welds or nor less than the minimum specified for plate thickness in Table 12/3:

2A – D1 L1

Lo = -------------                                             Equation (12/37)

                 D

Where,

Lo is size of fillet weld around outer periphery of pad, in mm,

L1 is size fillet weld around inner periphery of pad, in mm,

A is cross-sectional area of opening in shell (based on minimum thickness in square mm see regulation 463 ),

D is outer diameter of pad, in mm,

D1 is inner diameter of pad, in mm.

Tables and formulae are shown in their extracted layout. Alignment, superscripts and subscripts may be lost. The Gazette page image is authoritative.

Referenced provisions

Reg. 463

Independent explanation — not the law · draft · engineer review in progress

In short

Regulation 502 sizes the outer fillet weld that attaches a circular pad to a shell plate, for example for flanged mountings.

Key points

  • The outer weld size Lo comes from Equation (12/37): Lo = (2A − D1 L1) / D, where:
  • L1 is the inner fillet weld size (mm);
  • A is the cross-sectional area of the shell opening in square mm, based on minimum thickness (see regulation 463);
  • D and D1 are the outer and inner diameters of the pad (mm).

Watch out

  • The outer weld must also be at least as large as the inner welds, and at least the minimum for the plate thickness in Table 12/3. Use whichever gives the largest weld.

Written by IBRsource editors · last edited 2026-11-20. Explanations simplify and are not a design method, testing procedure or authorisation. Requirements come from the complete regulations, the Gazette and approved documentation.

Comparison pending: the IBR 1950 text in force on 30 September 2026 is not yet established for this provision, so no change is claimed (how this works).

Orientation hints (unverified)

These candidates come from automated heading matching against DPIIT's scanned historical print edition of IBR 1950. That edition uses imperial units and riveted-construction provisions, so it is not the operative 2026 predecessor text. Regulation numbers alone never prove equivalence.

Historical 1950-edition reg.Heading as OCR'dHeading similaritySource image
411Pads100%Chapter X (DPIIT scan), image 4
600Pads Welded to shell or the attachment of Flanged Mountings100%Chapter XII (DPIIT scan), image 15
107Welded Shell Plates77%Chapter III (DPIIT scan), image 1
IBR 1950 regulation 411 as last published in the DPIIT web edition (archived 2022)

Unofficial archived copy, not verified; see the regulation 411 page for its amendments.

Reg. 410, Reg. 411, Reg. 412
RIVETED STEEL BOILERS

Flange-Thickness and Drilling

The thickness and drilling of flanges of standpipes shall be in accordance with the Appendix (E).



Reg. 411
RIVETED STEEL BOILERS

Pads

These shall comply with Regulation 155.



Reg. 412
RIVETED STEEL BOILERS

Unstayed Flat-End Plates

The working pressure of unstayed flat-end plates shall be determined by the following formula:

W.P. = 2S(t-2)² Eqn. (98)
D²

Where,

t = thickness of plate in thirty-seconds of an inch.
W.P. = Working pressure in pounds per square inch.
D = Diameter in inches of the pitch circle of the bolts or rivets when the plate is attached to an outside flange or the internal diameter of the shell when the plate is attached to an inside flange.
S = Minimum tensile stress of the plate in tons per square inch.

In no case shell the thickness of an unstayed flat-end plate be less than 3/8 inch.

Where an unstayed flat-end plate is pierced for electrodes or other fittings by openings having a diameter not greater than 2 ½ inches and the pitch of the openings in inches is not less than four times the diameter of the openings in inches, compensation is not required.

Where the diameter of the openings in an unstayed flat-end plate is greater than 2 ½ inches or the pitch in inches is less than four times the diameter of the openings, adequate compensation shall be provided in the manner described in Regulations 170, 171 and 186.

IBR 1950 regulation 600 as last published in the DPIIT web edition (archived 2022)

Unofficial archived copy, not verified; see the regulation 600 page for its amendments.

Reg. 598, Reg. 599, Reg. 600, Reg. 601

Uptakes of Vertical Boilers

The working pressure for uptake tubes of vertical boilers shall be determined by the following formula:-

(i) When an internal liner is not fitted:-

W.P. = 100 (t-2) Equation XII/33.
D
(ii) When an internal liner is fitted extending below the low water level:-

W.P. = 725 x (t-1)² Equation XII/34.
D (L+24)

Where,

W.P. is working pressure in pounds per square inch.
t is thickness of the uptake in thirty seconds of an inch.
D is external diameter in inches.
L is length of the uptake in inches, measured between the circumferential seams.

In no case shall the thickness of an uptake tube be less than 3/8 inch.



Reg. 599

Cross Tubes

Internal diameter of cross tubes shall not exceed 12 inches. The working pressure of the tubes shall be determined by the following formula:-

W.P. = 200(t-7) Equation XII/35.
D

t is thickness in thirty seconds of an inch of the cross tube.
D is internal diameter in inches of the cross tube.

In no case shall be thickness of a cross tube be less than 5/16 inch


Reg. 600

Pads Welded to shell or the attachment of Flanged Mountings

(see Fig XII/90) -The size of outer peripheral fillet welds by which circular pads are attached to shell plates shall be determined by the following formula XII/36, but shall in no case be less than the inner welds or nor less than the minimum specified for plate thickness in Table XII/3:-

Lo = 2A-D1 L1 Equation XII/36
Do

Where,

Lo is size of fillet weld around outer periphery of pad, in inches.
L1 is size of fillet weld around inner periphery of pad, in inches.
A is cross sectional area of opening in shell (based on minimum thickness In square inches see Regulation 571.
Do is outer diameter of pad, in inches
D1 is inner diameter of pad, in inches.


Reg. 601

Hydraulic and Hammer Tests:-

a)
(i) Class I Boilers – Each Class I Boiler shall, on completion of all welding and/or repairs and after heat-treatment, be subjected to a hydraulic test of 1.5 times the design pressure without any indication of weakness or defect.
(ii) Class II and Class III Boilers – Each Class II and Class III boilers shall be tested to a pressure twice the design pressure.
b)
(i) The test shall be witnessed by the Inspecting Authority or Inspecting Officer.
(ii) The test pressure shall be maintained for a period not less than 30 minutes.

It is important in the interest of safety that the boiler be properly vented, so as to prevent the formation of air pockets, before the test pressure as applied.

NOTE:-

1. It is recommended that the temperature of the water should not be less than 7°C during the hydraulic test.

2. It is further recommended that before the boiler is approached for close examination, the pressure shall be reduced to not less than 1.1 times the design pressure and not more than 0.9 times the hydraulic test pressure.

3. On completion of hydraulic test, release of pressure shall be gradual.

4. Deflection of different pressure parts shall be examined carefully and there shall not be any permanent set after release of pressure
c) If any repairs are found to be necessary during or subsequent to the hydraulic pressure test, the boiler shall again be subjected to the pressure test specified above after completion of the repairs and after any heat treatment.

NOTE:-
Observations and remarks of Inspecting Officer/Inspecting Authority should be recorded for filming with makers’ papers.
IBR 1950 regulation 107 as last published in the DPIIT web edition (archived 2022)

Unofficial archived copy, not verified; see the regulation 107 page for its amendments.

Reg. 105, Reg. 106, Reg. 107
SHELLS, ANGLE RINGS, BUTT STRAPS, ETC.
Angle Rings

Angle rings for the attachment of end plates to shell plates and/or flue sections shall be rolled or machined so that they fit closely to the flat and cylindrical surfaces to be connected, and shall be machined or machine gas cut on the caulking edges.

Reg. 106
SHELLS, ANGLE RINGS, BUTT STRAPS, ETC.

Thickness of Shell Angle Rings

Where shell plates and end plate are connected by means of an external angle ring, the angle rings shall be no less in thickness than as follows :-

(1) For shell plates upto and including 5/8 inch in thickness. 10 per cent in excess of the thickness of the shell plate.
(2) For shell plate exceeding 5/8 inch in thickness and upto and including 1 inch in thickness.
90 per cent of the thickness but not less than 11/16 inch.
(3) For shell plates over 1 inch in thickness. Made from angle bar having a section thickness of 1 inch.


Reg. 107
SHELLS, ANGLE RINGS, BUTT STRAPS, ETC.

Welded Shell Plates

The requirements of welded shells shall be covered by the provisions made in the Regulations in Chapter V or Chapter XII, as the case may be.

The working pressure of such shells shall comply with Regulation 176 where J = 100 and C = 2.75.

Images of the official Gazette pages that contain this regulation. Click to zoom. Compare word by word before relying on the extracted text.

Instrument
Indian Boiler Regulations, 2026 (made by the Central Boilers Board under s.40 of the Boilers Act, 2025)
Notification
F.No. P-30014/3/2021-Boiler dated 7 Aug 2026
Published
Gazette of India, Extraordinary, Part III Sec. 4, No. 596, 1 Oct 2026 (CG-DL-E-06102026-276813)
In force
1 Oct 2026 (reg. 1(3): date of publication in the Official Gazette)
Printed Gazette page
796–797
PDF page index
796–797 · open official e-Gazette PDF
Extraction
pdftotext layout mode, sequential regulation detector · text hash 77869a35fb88ccbc
Verification
Official text — not yet verified
Amendments checked
None known after 1 Oct 2026 as of build date (not a guarantee). Amendment log
How to cite

Indian Boiler Regulations, 2026, reg. 502, Regulation 502, Gazette of India, Extraordinary, Part III—Section 4, No. 596, 1 October 2026, printed p.796–797. https://egazette.gov.in/WriteReadData/2026/276813.pdf (text consulted via IBRsource, 2026-11-23).

The citation refers to the government publication. Cite the Gazette, not this website.