Chapter 12 — Shell Type Boilers of Welded Construction

110 regulations (395–504)Gazette starts p.756

Regulation headings are not yet verified against the official Gazette. Entries in [square brackets] are editorial navigation labels, not Gazette wording.

← Chapter 11: Standard Conditions for the Design and Construction of Economisers, Feed Pipes, Feed Heaters and Other Similar Vessels · Chapter 13: Qualification Tests for Welders and Welding Operators → · Figures in Chapter 12

  1. 395. Application
  2. 396. General requirements
  3. 397. Equipment of workshop
  4. 398. Materials of construction
  5. 399. Welding consumables
  6. 400. Plain and Stay Tubes
  7. 401. Construction and workmanship
  8. 402. Preparation of plates
  9. 403. Stress relieving
  10. 404. Cylindrical shells
  11. 405. Circularity
  12. 406. End plates, crown plates and tube plates
  13. 407. Internal flues
  14. 408. Uptakes
  15. 409. Cross-tubes
  16. 410. Furnace of vertical boilers
  17. 411. Hemispherical Fireboxes
  18. 412. Loco-type fireboxes
  19. 413. Water-cooled combustion chambers
  20. 414. Bar stays and firebox stays
  21. 415. Bar stays
  22. 416. Firebox Stays
  23. 417. Girder stays for firebox and combustion chamber crowns
  24. 418. Gusset Stays
  25. 419. Access
  26. 420. Manhole frames, mouthpieces and doors
  27. 421. Internal doors
  28. 422. Seatings for mountings
  29. 423. Stand Pipes
  30. 424. Saddles
  31. 425. Pads
  32. 426. Attachment of standpipes
  33. 427. Attachment of pads
  34. 428. Attachment of water and pressure gauges
  35. 429. Bolts and Nuts
  36. 430. Compensating plates
  37. 431. Definition of the term ‘fusion weld’
  38. 432. Methods of welding
  39. 433. Types of welded shell seams
  40. 434. Repairs to welded seams
  41. 435. Tests on welded seams of shell
  42. 436. Test of Class I boilers
  43. 437. Tensile tests
  44. 438. Cold bend tests
  45. 439. Impact tests
  46. 440. Macro and micro examinations
  47. 441. Additional tests before rejection
  48. 442. Specimens after tests
  49. 443. Radiographic examinations
  50. 444. Test for class II boilers
  51. 445. Tensile test
  52. 446. Cold bend tests
  53. 447. Nick-break specimen
  54. 448. Additional tests before rejection
  55. 449. Specimen after tests
  56. 450. Radiographic or ultrasonic examination
  57. 451. Test for Class III boilers
  58. 452. Radiographic or ultrasonic examination
  59. 453. Heat treatment
  60. 454. Classification of fusion-welded boilers
  61. 455. Shells
  62. 456. Horizontal shelves of tube plates forming part of the Shell
  63. 457. Dished end plates for Lancashire and Cornish boilers
  64. 458. Dished Ends subject to internal pressure
  65. 459. [No printed heading] “Nothing in regulation 458 shall preclude the use…”
  66. 460. Dished Ends subject to external pressure
  67. 461. Hemispherical Crowns
  68. 462. Manholes and other openings in Shells
  69. 463. Compensation for openings in Shells
  70. 464. Raised manhole frames, cover plates and joint bolts
  71. 465. Standpipes and branches
  72. 466. Stayed flat surfaces (other than crowns of vertical boilers)
  73. 467. Flat crown plates for vertical boilers
  74. 468. Wide water spaces between and around tube nests
  75. 469. Flat tube plates and tubes nests
  76. 470. Manhole openings in flat plates
  77. 471. Plain Tubes
  78. 472. Pitch of Tubes
  79. 473. Stay Tubes
  80. 474. Compression of Tube Plates
  81. 475. Girders for fire-box and combustion chamber crowns
  82. 476. Girder sling stays
  83. 477. Stays for fire boxes and circular furnaces
  84. 478. Fire-box crown stays for Loco-type boilers
  85. 479. Longitudinal bar stays
  86. 480. Loads on stay tubes and bar stays
  87. 481. Flat plate margins
  88. 482. Breathing space
  89. 483. For boilers as per clause (a)of sub-regulation (9) of regulation 407
  90. 484. Forboilers as per clause (d) of sub-regulation (9) of regulation 407
  91. 485. For Boilers not covered under regulations 483 and 484
  92. 486. Gusset Link, brace and similar stays
  93. 487. Furnaces
  94. 488. Plain furnaces
  95. 489. Furnace components
  96. 490. Corrugated furnaces
  97. 491. Tolerances and allowances
  98. 492. Out-of-roundness
  99. 493. Stiffeners
  100. 494. Circular reversal chambers
  101. 495. Plain furnaces of vertical boilers
  102. 496. Corrugated fireboxes of vertical boilers
  103. 497. Hemispherical furnaces of vertical boilers
  104. 498. Foundations of Vertical Boiler Furnaces
  105. 499. Foundations of Loco type boiler fireboxes
  106. 500. Uptakes of vertical boilers
  107. 501. Cross tubes
  108. 502. Pads welded to shell or the attachment of flanged mountings
  109. 503. Hydraulic test
  110. 504. Safety valves