BETAIndependent engineering reference. Source-text verification is ongoing.Verification ongoing.Verification status →
IBRsourceIndian Boiler Regulations, made clear

Methodology

1. Sources

Regulatory text is sourced only from official government publications: the Gazette of India (e-Gazette and DPIIT-hosted copies) and India Code. Original explanations and illustrations are developed independently. A SHA-256 checksum is recorded for each source file to identify the exact copy processed (a matching checksum confirms file identity, not legal authenticity or correctness); all files are listed in the source registry. Secondary sources are used for the IBR 1950 only: DPIIT's former web edition of the regulations, as archived by the Internet Archive (2019–2024, the latest form of each page) and as a saved printout from 2008. They supply the 1950 text shown on the IBR 1950 pages and the 2007 amendment, which is not otherwise available. It is always labelled as such and never presented as Gazette text.

2. Extraction

The English portion of the IBR 2026 Gazette (from printed page 489) is converted to text with layout preserved. A sequential detector finds regulation headings 1 to 596 in order. Each regulation keeps its printed Gazette page and its PDF page index, which are recorded separately. Each regulation is flagged automatically if it contains tables, formulae, figure references or characters that could not be read. Symbols printed in a symbol font (≥, ≤, √, Greek letters) are recovered separately and tested on every rebuild. Ruled tables are read directly from the Gazette PDF, cell by cell, so rows, columns and merged cells follow the printed table; every line of every cell is checked automatically against its Gazette page. Tables without ruling lines are rebuilt from the text layout and say so. Each table keeps the original extracted text in a collapsed panel.

3. Verification

Every page of official text shows one status: Official text — not yet verified (with one warning on that page) or Official text — checked against Gazette. The same system applies to regulations, appendices, forms, Act sections, amendment notifications and rules. The workflow is: automatic extraction → comparison with the source page → corrections → independent review → verified. Extraction is only a draft. A provision is marked checked against Gazette only after a reviewer checks the complete provision against the Gazette page image shown on the page, including clauses, formulae, tables, symbols and footnotes, paying particular attention to numbers, units, decimal points, symbols, subscripts, provisos, table headings and footnotes. The Gazette page reference, the date, the reviewer and the source file version are recorded. A whole appendix or Act counts as checked only when all of its text has passed. Reviews of the explanations (including AI-assisted reviews) never mark the official text as verified. Corrections are made to the text only to match the Gazette, never to "improve" it. Community feedback helps decide what to check first.

4. Change tracker (crosswalk)

Regulation numbers are not stable across editions, so the tracker links provisions many-to-many. Every candidate relationship has a review status (machine suggestion, under review, verified) and, once verified, a change classification: unchanged, wording changed, technical requirement changed, new, removed, renumbered, split, merged, relocated or cross-reference changed.

Automation only suggests candidates, by heading and text similarity. Every machine suggestion is "uncertain". A reviewer confirms the pair, cites exact old and new wording with page references, and writes "what changed" separately from "what it means".

The predecessor for IBR 2026 is the IBR 1950 as in force immediately before 1 October 2026. That text must be rebuilt from the 1950 notification and every amendment (the official list since 1990 is in the source registry).

5. Explanations

Explanations are original writing. First drafts were written with AI assistance from the extracted Gazette text, then checked automatically: numbers in an explanation that do not appear in the provision are flagged for source verification. This check cannot establish that an explanation is technically correct. They remain drafts until a person with boiler experience reviews them. Each states which provision it explains and its review status. Explanations never tell readers that an existing approved design is now non-compliant.

6. Figures and drawings

Gazette figures are shown as exact crops of the official pages. They are also offered as traced vectors (SVG and DXF, made with the open-source potrace tool) so they can be placed in drawings. Traced vectors reproduce the printed figure; they are not to scale and are not re-dimensioned.

Most figures with a drawing (as opposed to a table) are also redrawn as reconstructed CAD: true lines, arcs and circles, section hatching, dimension entities and every printed label as editable text. Printed dimensions are reproduced as annotations, and drawn at that size where the figure gives enough information; otherwise the geometry is schematic, follows the printed proportions and is not to scale. Each reconstruction is compared against the Gazette crop for missing labels, values and shape. The Gazette wording is preserved unchanged, including apparent misprints, which are noted in the figure's record rather than silently corrected. Where a reconstruction exists it replaces the traced version. Technical review is pending.

Original drawings are drawn independently from scripts in FreeCAD and Python. Each has a manifest recording its basis, units, precision (schematic or dimensioned), checks and fingerprint. Every drawing carries a small IBRsource.com mark on its own layer or group, so it can be deleted in one step. For our original drawings, removing the mark does not remove the CC BY 4.0 attribution requirement; Gazette-derived figures are official matter, not our CC BY content.

7. Worked examples and calculators

Worked examples cite every formula exactly as printed, with its symbols, units and conditions, and use clearly labelled hypothetical inputs. Calculators exist only for well-scoped formulae. Each calculator is tested against published test vectors, and the expected values are computed independently (for regulation 171, the regulation's own printed examples). Where the printed formula is ambiguous (for example the one-line flattening formula in regulation 48(4)), the page says so. All examples are drafts pending engineering review.