Indian Boiler Regulations, 2026 · Chapter 12 · Shell Type Boilers of Welded Construction
Regulation 412. Loco-type fireboxes
Not yet checked against the official Gazette; verify before relying on it.
412. Loco-type fireboxes.─ (1) Loco-type firebox wrapper plate sides shall preferably be tapered. The water space at the bottom between the fire-box and the shell shall be not less than 63 mm.
(2)Where the firebox tube plate or fire-hole plate is flanged for connection to the wrapper plate, the weld shall be located between the commencement of curvature of the flange and first row of screwed stays.
(3)Rings for fire-hole mouthpieces of foundation rings shall be made of materials as specified in chapter -2.
(4)Z-sections shall not be used for foundation rings. The attachment of the firebox to the outer casing shall be in accordance with Figures 12/37 or 12/30 or 12/31.
(5)The method of attachment of fire hole mouthpieces shall be in accordance with Figures 12/40 or, where the outer casing and the firebox plate are flanged towards the water side to form the fire hole, a ring of screwed stays located at not more than half the average pitch of the stays distant from the commencement of the curvature of the flanging shall be provided (see Figure 12/45.
Figures cited in this regulation (5, exact crops of the Gazette)

View Gazette page 804 · figure catalogue
Auto-traced outline: SVG · DXF (not to scale, may copy print defects)

View Gazette page 804 · figure catalogue
Auto-traced outline: SVG · DXF (not to scale, may copy print defects)

View Gazette page 805 · figure catalogue
Reconstructed CAD: DXF · SVG · Preview (redrawn, checked against the print; technical review pending)

View Gazette page 806 · figure catalogue
Auto-traced outline: SVG · DXF (not to scale, may copy print defects)

View Gazette page 808 · figure catalogue
Auto-traced outline: SVG · DXF (not to scale, may copy print defects)
In short
Regulation 412 covers loco-type fireboxes in welded boilers.
Key points
- (1) Wrapper plate sides should preferably be tapered. The bottom water space between firebox and shell must be at least 63 mm.
- (2) Where the tube plate or fire-hole plate is flanged to join the wrapper plate, the weld must sit between the start of the flange curvature and the first row of screwed stays.
- (3) Rings for fire-hole mouthpieces and foundation rings are made of materials specified in Chapter 2.
- (4) The firebox is attached to the outer casing as shown in the listed figures.
- (5) Fire hole mouthpieces follow the listed figure. Where the outer casing and firebox plate are flanged towards the water side to form the fire hole, a ring of screwed stays is needed, no further than half the average stay pitch from where the flanging curvature starts.
Watch out
- (4) Z-sections must not be used for foundation rings.
Written by IBRsource editors · last edited 2026-11-20. Explanations simplify and are not a design method, testing procedure or authorisation. Requirements come from the complete regulations, the Gazette and approved documentation.
Comparison pending: the IBR 1950 text in force on 30 September 2026 is not yet established for this provision, so no change is claimed (how this works).
Orientation hints (unverified)
These candidates come from automated heading matching against DPIIT's scanned historical print edition of IBR 1950. That edition uses imperial units and riveted-construction provisions, so it is not the operative 2026 predecessor text. Regulation numbers alone never prove equivalence.
No candidate heading found in the historical print edition.
Images of the official Gazette pages that contain this regulation. Click to zoom. Compare word by word before relying on the extracted text.

Indian Boiler Regulations, 2026, reg. 412, Regulation 412, Gazette of India, Extraordinary, Part III—Section 4, No. 596, 1 October 2026, printed p.760. https://egazette.gov.in/WriteReadData/2026/276813.pdf (text consulted via IBRsource, 2026-11-23).
The citation refers to the government publication. Cite the Gazette, not this website.