Indian Boiler Regulations, 2026 · Chapter 12 · Shell Type Boilers of Welded Construction

Regulation 490. Corrugated furnaces

Official text — not yet verifiedGazette 1 Oct 2026 · printed pp. 792–793Formula / symbols

Not yet checked against the official Gazette; verify before relying on it.

Reproduced from the Gazette of India · verification status above

490.Corrugated furnaces.─ The maximum allowable working pressure of corrugated furnaces shall be determined using the equation 12/27, but the thickness shall not be less than 10 mm and shall not exceed 22 mm. Calculated value of ‘I’ and ‘F’ for some of the corrugations are given in figure 12/119 for other shapes and sizes calculations need to be made from basic principles.

𝑃= 2𝐹𝐸𝑡(1+0.1 𝑑 𝐿 ) Equation (12/27)

𝑆1𝑏 𝑑 [1+ 5𝑑 𝑒−𝑐 3 𝐹𝑊𝐷𝑢 ]

800 𝐼 {1+ 𝐿 ( 𝑊 ) }

Parts of this extracted text look garbled; read the Gazette page before using any value.

Tables and formulae are shown in their extracted layout. Alignment, superscripts and subscripts may be lost. The Gazette page image is authoritative.

Figures cited in this regulation (1, exact crops of the Gazette)

Gazette Fig. 12/119: Second Moments of Area and Cross-Sectional Area F (Contd.)…
Fig. 12/119Second Moments of Area and Cross-Sectional Area F (Contd.)…
View Gazette page 833 · figure catalogue
Auto-traced outline: SVG · DXF (not to scale, may copy print defects)
Independent explanation — not the law · draft · engineer review in progress

In short

Regulation 490 sets the maximum allowable working pressure of corrugated furnaces using Equation (12/27). Thickness must be at least 10 mm and not more than 22 mm.

Key points

  • The equation uses the symbols in regulation 487, including the corrugation section properties I and F.
  • Figure 12/119 gives calculated I and F values for some corrugation shapes. For other shapes and sizes, calculate them from basic principles.
  • Where stiffeners are fitted on corrugations, see regulation 493.

Watch out

  • The equation did not extract cleanly. Check the Gazette page for its exact form.

Written by IBRsource editors · last edited 2026-11-20. Explanations simplify and are not a design method, testing procedure or authorisation. Requirements come from the complete regulations, the Gazette and approved documentation.

Comparison pending: the IBR 1950 text in force on 30 September 2026 is not yet established for this provision, so no change is claimed (how this works).

Orientation hints (unverified)

These candidates come from automated heading matching against DPIIT's scanned historical print edition of IBR 1950. That edition uses imperial units and riveted-construction provisions, so it is not the operative 2026 predecessor text. Regulation numbers alone never prove equivalence.

Historical 1950-edition reg.Heading as OCR'dHeading similaritySource image
221Corrugated Furnaces of Horizontal Boilers100%Chapter IV (DPIIT scan), image 14
IBR 1950 regulation 221 as last published in the DPIIT web edition (archived 2022)

Unofficial archived copy, not verified; see the regulation 221 page for its amendments.

Reg. 220, Reg. 221, Reg. 222

FURNACES

Plain Furnaces of Horizontal Boilers

For plain furnaces or furnaces strengthened by Adamson or other joints or stiffeners of sufficient strength and for the semi-cylindrical tops of fire-boxes and bottom of combustion chambers where the sides are securely stayed, the working pressure shall not exceed the smaller of the values obtained from the following formulae :-
W. P. = C X (t - 1)2 Eqn.(57)
D ( L + 24 )

W. P. = C1 X {10 ( t - 1) - L ) Eqn.(58)
D

Where
d = the external diameter of the furnace or chamber top or bottom in inches

t = the thickness of the furnace plate in 32nds of an inch.

L = the length of the furnace or other part in inches measured between points of substantial support, i.e. centres of rows of rivets in end seams or commencement of curvature of flange, whichever is applicable.

C = 1450 where the longitudinal seams of steel furnaces are welded and 1300 where they are riveted,

C = 725 where the longitudinal seams of circular copper fireboxes or furnaces are fitted with double butt straps and 650 where they are lapped,

C1 = 50 where the longitudinal seams of steel furnaces are welded and 45 where they are riveted,

C1 = 25 where the longitudinal seams of circular copper fireboxes or furnaces are fitted with double butt straps and 22.5 where they are lapped.

Reg. 221

FURNACES

Corrugated Furnaces of Horizontal Boilers

The maximum working pressure to be allowed on corrugated furnaces shall be determined by the following formula -
W. P. = C ( t - 1 ) Eqn.(59)
D

where
D is the least external diameter in inches measured at the bottom of the corrugations on the water side.

t is the thickness of the furnace plate in 32nds of an inch measured at the bottom of the corrugation or chamber,

C = 480 for the Fox, Morrison, Deighton, Purves,, and other similar furnaces and 510 for the leeds Forge Bulb Suspension Furnace.

Reg. 222

FURNACES

Plain Furnaces of Vertical Boilers

The same formulae as for the plain furnaces of horizontal boilers shall be used, but where the furnaces are tapered the diameter to be taken for calculation purposes shall be the mean of that at the top and of that at the bottom where it meets the substantial support from flange or ring. The length for the same purpose shall be the distance from the centre of the row of rivets connecting the crown and the body of the furnace to the substantial support at the bottom of the furnace, or to a row of screwed stays connecting the furnace to the shell, provided that the pitch of stays at the furnace does not exceed 14 times the thickness of the furnace plate when the stays are riveted at their ends or 16 times when the stays are fitted with nuts. Such screwed stays shall be in diameter over the threads not less than twice the thickness of the furnace plate and in no case less than 3/4" diameter {See Reg.135 (d)}.

Images of the official Gazette pages that contain this regulation. Click to zoom. Compare word by word before relying on the extracted text.

Instrument
Indian Boiler Regulations, 2026 (made by the Central Boilers Board under s.40 of the Boilers Act, 2025)
Notification
F.No. P-30014/3/2021-Boiler dated 7 Aug 2026
Published
Gazette of India, Extraordinary, Part III Sec. 4, No. 596, 1 Oct 2026 (CG-DL-E-06102026-276813)
In force
1 Oct 2026 (reg. 1(3): date of publication in the Official Gazette)
Printed Gazette page
792–793
PDF page index
792–793 · open official e-Gazette PDF
Extraction
pdftotext layout mode, sequential regulation detector · text hash 2161cfb96faaa7db
Verification
Official text — not yet verified
Amendments checked
None known after 1 Oct 2026 as of build date (not a guarantee). Amendment log
How to cite

Indian Boiler Regulations, 2026, reg. 490, Regulation 490, Gazette of India, Extraordinary, Part III—Section 4, No. 596, 1 October 2026, printed p.792–793. https://egazette.gov.in/WriteReadData/2026/276813.pdf (text consulted via IBRsource, 2026-11-23).