Regulation 431. Definition of the term ‘fusion weld’

Official text — not yet verifiedGazette 1 Oct 2026 · printed p. 764

Not yet checked against the official Gazette; verify before relying on it.

Reproduced from the Gazette of India · verification status above

431. Definition of the term ‘fusion weld’.─ (1) For the purpose of this chapter, the term ‘fusion weld’ is applicable to all welded seams made by the metal arc process with covered electrodes or by any other electric arc process in which the arc stream and the deposited weld metal are shielded from atmospheric contamination.

(2)The relevant provisions of this chapter shall also apply to the single run or heavy run welding process and that welded boilers manufactured by that process shall comply with all regulations of this chapter excepting those in which divergence is necessary solely because of special requirements essential for the most efficient utilisation of that process. Thus all regulation governing quality of material construction workmanship, and testing (both non-destructive and otherwise) are applicable.

(3)Where welded shells conforming to the regulations of this chapter are made by single or heavy run process, it shall be understood that regulations 431,432 and 433 do not apply in their entirety. The method of making the welds shall be approved by the Inspecting Authority.

Referenced provisions

Reg. 432 · Reg. 433

Independent explanation — not the law · draft · engineer review in progress

In short

Defines "fusion weld" for this chapter and explains how the chapter applies to boilers made by the single run or heavy run welding process.

Key points

  • (1) A fusion weld is any welded seam made by the metal arc process with covered electrodes, or by any other electric arc process where the arc stream and deposited weld metal are shielded from atmospheric contamination.
  • (2) Boilers made by the single run or heavy run process must comply with all regulations of this chapter, except where a difference is needed solely because of the special requirements of that process. All rules on material quality, construction, workmanship and testing (non-destructive and otherwise) still apply.
  • (3) For welded shells made by the single or heavy run process, regulations 431, 432 and 433 do not apply in their entirety. The welding method must be approved by the Inspecting Authority.

Written by IBRsource editors · last edited 2026-11-20. Explanations simplify and are not a design method, testing procedure or authorisation. Requirements come from the complete regulations, the Gazette and approved documentation.

Comparison pending: the IBR 1950 text in force on 30 September 2026 is not yet established for this provision, so no change is claimed (how this works).

Orientation hints (unverified)

These candidates come from automated heading matching against DPIIT's scanned historical print edition of IBR 1950. That edition uses imperial units and riveted-construction provisions, so it is not the operative 2026 predecessor text. Regulation numbers alone never prove equivalence.

No candidate heading found in the historical print edition.

Images of the official Gazette pages that contain this regulation. Click to zoom. Compare word by word before relying on the extracted text.

Instrument
Indian Boiler Regulations, 2026 (made by the Central Boilers Board under s.40 of the Boilers Act, 2025)
Notification
F.No. P-30014/3/2021-Boiler dated 7 Aug 2026
Published
Gazette of India, Extraordinary, Part III Sec. 4, No. 596, 1 Oct 2026 (CG-DL-E-06102026-276813)
In force
1 Oct 2026 (reg. 1(3): date of publication in the Official Gazette)
Printed Gazette page
764
PDF page index
764 · open official e-Gazette PDF
Extraction
pdftotext layout mode, sequential regulation detector · text hash 974b8bc8d46c9f6c
Verification
Official text — not yet verified
Amendments checked
None known after 1 Oct 2026 as of build date (not a guarantee). Amendment log
How to cite

Indian Boiler Regulations, 2026, reg. 431, Regulation 431, Gazette of India, Extraordinary, Part III—Section 4, No. 596, 1 October 2026, printed p.764. https://egazette.gov.in/WriteReadData/2026/276813.pdf (text consulted via IBRsource, 2026-11-23).

The citation refers to the government publication. Cite the Gazette, not this website.

Help improve this page

Engineers like you keep IBRsource accurate. Every checked correction or tip helps the next reader.