Indian Boiler Regulations, 2026 · Chapter 3 · Construction and Workmanship
Regulation 94. Furnaces
Not yet checked against the official Gazette; verify before relying on it.
94. Furnaces.─(1)No furnace or firebox top, whether plain or corrugated, shall exceed 22 mm in thickness, and all circular sectioned furnaces when new, shall be as near the truly circular form as the type of joint will permit.
(2)The use of Z angle rings for furnace foundation seams shall be prohibited.
(3)Furnace crowns, uptakes and other plates not in tension may be joined by fusion welding provided the conditions laid down in regulation 95 to 101 are complied with. The end connections of such plates to the shell or shell crown shall also comply with such conditions. This construction shall not apply to furnaces of Lancashire and Cornish type boilers consisting wholly or plain sections.
Parts of this extracted text look garbled; read the Gazette page before using any value.
In short
Regulation 94 sets general rules for furnaces: a maximum thickness, circularity, a ban on Z angle rings, and when furnace parts may be fusion welded.
Key points
- (1) No furnace or firebox top, plain or corrugated, may exceed 22 mm in thickness. New circular furnaces must be as near truly circular as the joint type allows.
- (2) Z angle rings must not be used for furnace foundation seams.
- (3) Furnace crowns, uptakes and other plates not in tension may be fusion welded if the conditions of regulations 95 to 101 are met, including for their end connections to the shell or shell crown.
Watch out
- The welding permission in (3) does not apply to furnaces of Lancashire and Cornish type boilers made of plain sections. The wording here is garbled in the extracted text, so check the Gazette page.
Written by IBRsource editors · last edited 2026-11-20. Explanations simplify and are not a design method, testing procedure or authorisation. Requirements come from the complete regulations, the Gazette and approved documentation.
Comparison pending: the IBR 1950 text in force on 30 September 2026 is not yet established for this provision, so no change is claimed (how this works).
Orientation hints (unverified)
These candidates come from automated heading matching against DPIIT's scanned historical print edition of IBR 1950. That edition uses imperial units and riveted-construction provisions, so it is not the operative 2026 predecessor text. Regulation numbers alone never prove equivalence.
| Historical 1950-edition reg. | Heading as OCR'd | Heading similarity | Source image |
|---|---|---|---|
| 122 | Furnaces of Horizontal Boilers | 100% | Chapter III (DPIIT scan), image 3 |
| 221 | Corrugated Furnaces of Horizontal Boilers | 100% | Chapter IV (DPIIT scan), image 14 |
| 592 | Furnaces and Flue Sections of Horizontal Boilers | 100% | Chapter XII (DPIIT scan), image 13 |
Amendment history of the candidate IBR 1950 regulations: Reg. 592 (6 amendments)
IBR 1950 regulation 122 as last published in the DPIIT web edition (archived 2022)
Unofficial archived copy, not verified; see the regulation 122 page for its amendments.
| Reg. 122 FURNACES Furnaces of Horizontal boilers
|
IBR 1950 regulation 221 as last published in the DPIIT web edition (archived 2022)
Unofficial archived copy, not verified; see the regulation 221 page for its amendments.
| Reg. 220, Reg. 221, Reg. 222 FURNACES Plain Furnaces of Horizontal Boilers For plain furnaces or furnaces strengthened by Adamson or other joints or stiffeners of sufficient strength and for the semi-cylindrical tops of fire-boxes and bottom of combustion chambers where the sides are securely stayed, the working pressure shall not exceed the smaller of the values obtained from the following formulae :-
Where d = the external diameter of the furnace or chamber top or bottom in inches t = the thickness of the furnace plate in 32nds of an inch. L = the length of the furnace or other part in inches measured between points of substantial support, i.e. centres of rows of rivets in end seams or commencement of curvature of flange, whichever is applicable. C = 1450 where the longitudinal seams of steel furnaces are welded and 1300 where they are riveted, C = 725 where the longitudinal seams of circular copper fireboxes or furnaces are fitted with double butt straps and 650 where they are lapped, C1 = 50 where the longitudinal seams of steel furnaces are welded and 45 where they are riveted, C1 = 25 where the longitudinal seams of circular copper fireboxes or furnaces are fitted with double butt straps and 22.5 where they are lapped. Reg. 221 FURNACES Corrugated Furnaces of Horizontal Boilers The maximum working pressure to be allowed on corrugated furnaces shall be determined by the following formula -
where D is the least external diameter in inches measured at the bottom of the corrugations on the water side. t is the thickness of the furnace plate in 32nds of an inch measured at the bottom of the corrugation or chamber, C = 480 for the Fox, Morrison, Deighton, Purves,, and other similar furnaces and 510 for the leeds Forge Bulb Suspension Furnace. Reg. 222 FURNACES Plain Furnaces of Vertical Boilers The same formulae as for the plain furnaces of horizontal boilers shall be used, but where the furnaces are tapered the diameter to be taken for calculation purposes shall be the mean of that at the top and of that at the bottom where it meets the substantial support from flange or ring. The length for the same purpose shall be the distance from the centre of the row of rivets connecting the crown and the body of the furnace to the substantial support at the bottom of the furnace, or to a row of screwed stays connecting the furnace to the shell, provided that the pitch of stays at the furnace does not exceed 14 times the thickness of the furnace plate when the stays are riveted at their ends or 16 times when the stays are fitted with nuts. Such screwed stays shall be in diameter over the threads not less than twice the thickness of the furnace plate and in no case less than 3/4" diameter {See Reg.135 (d)}. |
IBR 1950 regulation 592 as last published in the DPIIT web edition (archived 2022)
Unofficial archived copy, not verified; see the regulation 592 page for its amendments.
| Reg. 592 | ||||||
|
| Next >>> |
Images of the official Gazette pages that contain this regulation. Click to zoom. Compare word by word before relying on the extracted text.

Indian Boiler Regulations, 2026, reg. 94, Regulation 94, Gazette of India, Extraordinary, Part III—Section 4, No. 596, 1 October 2026, printed p.563. https://egazette.gov.in/WriteReadData/2026/276813.pdf (text consulted via IBRsource, 2026-11-23).
The citation refers to the government publication. Cite the Gazette, not this website.