Indian Boiler Regulations, 2026 · Chapter 3 · Construction and Workmanship

Regulation 85. Welded shell plates

Official text — not yet verifiedGazette 1 Oct 2026 · printed p. 561

Not yet checked against the official Gazette; verify before relying on it.

Reproduced from the Gazette of India · verification status above

85.Welded shell plates.─ The requirements of welded shells shall be covered by the provisions made in regulations in Chapter -4 or Chapter -12, as the case may be.

Independent explanation — not the law · draft · engineer review in progress

In short

Regulation 85 is a pointer: requirements for welded shells are in the regulations of Chapter 4 or Chapter 12, as the case may be.

Written by IBRsource editors · last edited 2026-11-20. Explanations simplify and are not a design method, testing procedure or authorisation. Requirements come from the complete regulations, the Gazette and approved documentation.

Comparison pending: the IBR 1950 text in force on 30 September 2026 is not yet established for this provision, so no change is claimed (how this works).

Orientation hints (unverified)

These candidates come from automated heading matching against DPIIT's scanned historical print edition of IBR 1950. That edition uses imperial units and riveted-construction provisions, so it is not the operative 2026 predecessor text. Regulation numbers alone never prove equivalence.

Historical 1950-edition reg.Heading as OCR'dHeading similaritySource image
33Plates100%Chapter II (DPIIT scan), image 3
107Welded Shell Plates100%Chapter III (DPIIT scan), image 1
600Pads Welded to shell or the attachment of Flanged Mountings77%Chapter XII (DPIIT scan), image 15
IBR 1950 regulation 33 as last published in the DPIIT web edition (archived 2022)

Unofficial archived copy, not verified; see the regulation 33 page for its amendments.

Reg. 33
MATERIALS OF CONSTRUCTION

COPPER PLATES, STAY AND RIVET BARS

Plates

(a) Process.- The copper shall be fire-refined or electrolytic and hot-rolled from suitable cakes.

(b) Chemical Composition.- The chemical composition of the plates shall be as follows:-

Per cent.
Copper 99.2 minimum
Arsenic .30 to .50
Antimony 0.05 maximum
Bismuth 0.05 maximum
Oxygen 0.10 maximum

(c) Freedom from defects.- The plates shall be clean, smooth and free from defects and shall have a workmanlike finish. They shall be thoroughly annealed.

(d) Rolling Margin.- No plate shall be under the specified thickness at any part, not more than 5% over the calculated weight. The scrap margin, partly sheared and left attached, shall be not less than 3 inches at the ends and 1½ inches at each side.

(e) Tensile Tests.- One tensile test shall be taken from each plate as rolled.

The tensile breaking strength, from Standard Test Piece A, shall not be less than 14 tons per sq. inch with an elongation of not less than 35%.

(f) Hot and Cold Bend tests.- One hot (temperature between 1200°F and 1400°F) and one cold bend test shall be taken from each plate as rolled.

For either hot or cold bend tests, the test piece shall withstand being doubled over without fracture until the sides are touching and parallel.

IBR 1950 regulation 107 as last published in the DPIIT web edition (archived 2022)

Unofficial archived copy, not verified; see the regulation 107 page for its amendments.

Reg. 105, Reg. 106, Reg. 107
SHELLS, ANGLE RINGS, BUTT STRAPS, ETC.
Angle Rings

Angle rings for the attachment of end plates to shell plates and/or flue sections shall be rolled or machined so that they fit closely to the flat and cylindrical surfaces to be connected, and shall be machined or machine gas cut on the caulking edges.

Reg. 106
SHELLS, ANGLE RINGS, BUTT STRAPS, ETC.

Thickness of Shell Angle Rings

Where shell plates and end plate are connected by means of an external angle ring, the angle rings shall be no less in thickness than as follows :-

(1) For shell plates upto and including 5/8 inch in thickness. 10 per cent in excess of the thickness of the shell plate.
(2) For shell plate exceeding 5/8 inch in thickness and upto and including 1 inch in thickness.
90 per cent of the thickness but not less than 11/16 inch.
(3) For shell plates over 1 inch in thickness. Made from angle bar having a section thickness of 1 inch.


Reg. 107
SHELLS, ANGLE RINGS, BUTT STRAPS, ETC.

Welded Shell Plates

The requirements of welded shells shall be covered by the provisions made in the Regulations in Chapter V or Chapter XII, as the case may be.

The working pressure of such shells shall comply with Regulation 176 where J = 100 and C = 2.75.

IBR 1950 regulation 600 as last published in the DPIIT web edition (archived 2022)

Unofficial archived copy, not verified; see the regulation 600 page for its amendments.

Reg. 598, Reg. 599, Reg. 600, Reg. 601

Uptakes of Vertical Boilers

The working pressure for uptake tubes of vertical boilers shall be determined by the following formula:-

(i) When an internal liner is not fitted:-

W.P. = 100 (t-2) Equation XII/33.
D
(ii) When an internal liner is fitted extending below the low water level:-

W.P. = 725 x (t-1)² Equation XII/34.
D (L+24)

Where,

W.P. is working pressure in pounds per square inch.
t is thickness of the uptake in thirty seconds of an inch.
D is external diameter in inches.
L is length of the uptake in inches, measured between the circumferential seams.

In no case shall the thickness of an uptake tube be less than 3/8 inch.



Reg. 599

Cross Tubes

Internal diameter of cross tubes shall not exceed 12 inches. The working pressure of the tubes shall be determined by the following formula:-

W.P. = 200(t-7) Equation XII/35.
D

t is thickness in thirty seconds of an inch of the cross tube.
D is internal diameter in inches of the cross tube.

In no case shall be thickness of a cross tube be less than 5/16 inch


Reg. 600

Pads Welded to shell or the attachment of Flanged Mountings

(see Fig XII/90) -The size of outer peripheral fillet welds by which circular pads are attached to shell plates shall be determined by the following formula XII/36, but shall in no case be less than the inner welds or nor less than the minimum specified for plate thickness in Table XII/3:-

Lo = 2A-D1 L1 Equation XII/36
Do

Where,

Lo is size of fillet weld around outer periphery of pad, in inches.
L1 is size of fillet weld around inner periphery of pad, in inches.
A is cross sectional area of opening in shell (based on minimum thickness In square inches see Regulation 571.
Do is outer diameter of pad, in inches
D1 is inner diameter of pad, in inches.


Reg. 601

Hydraulic and Hammer Tests:-

a)
(i) Class I Boilers – Each Class I Boiler shall, on completion of all welding and/or repairs and after heat-treatment, be subjected to a hydraulic test of 1.5 times the design pressure without any indication of weakness or defect.
(ii) Class II and Class III Boilers – Each Class II and Class III boilers shall be tested to a pressure twice the design pressure.
b)
(i) The test shall be witnessed by the Inspecting Authority or Inspecting Officer.
(ii) The test pressure shall be maintained for a period not less than 30 minutes.

It is important in the interest of safety that the boiler be properly vented, so as to prevent the formation of air pockets, before the test pressure as applied.

NOTE:-

1. It is recommended that the temperature of the water should not be less than 7°C during the hydraulic test.

2. It is further recommended that before the boiler is approached for close examination, the pressure shall be reduced to not less than 1.1 times the design pressure and not more than 0.9 times the hydraulic test pressure.

3. On completion of hydraulic test, release of pressure shall be gradual.

4. Deflection of different pressure parts shall be examined carefully and there shall not be any permanent set after release of pressure
c) If any repairs are found to be necessary during or subsequent to the hydraulic pressure test, the boiler shall again be subjected to the pressure test specified above after completion of the repairs and after any heat treatment.

NOTE:-
Observations and remarks of Inspecting Officer/Inspecting Authority should be recorded for filming with makers’ papers.

Images of the official Gazette pages that contain this regulation. Click to zoom. Compare word by word before relying on the extracted text.

Instrument
Indian Boiler Regulations, 2026 (made by the Central Boilers Board under s.40 of the Boilers Act, 2025)
Notification
F.No. P-30014/3/2021-Boiler dated 7 Aug 2026
Published
Gazette of India, Extraordinary, Part III Sec. 4, No. 596, 1 Oct 2026 (CG-DL-E-06102026-276813)
In force
1 Oct 2026 (reg. 1(3): date of publication in the Official Gazette)
Printed Gazette page
561
PDF page index
561 · open official e-Gazette PDF
Extraction
pdftotext layout mode, sequential regulation detector · text hash ea987d1b31e92046
Verification
Official text — not yet verified
Amendments checked
None known after 1 Oct 2026 as of build date (not a guarantee). Amendment log
How to cite

Indian Boiler Regulations, 2026, reg. 85, Regulation 85, Gazette of India, Extraordinary, Part III—Section 4, No. 596, 1 October 2026, printed p.561. https://egazette.gov.in/WriteReadData/2026/276813.pdf (text consulted via IBRsource, 2026-11-23).

The citation refers to the government publication. Cite the Gazette, not this website.