Indian Boiler Regulations, 2026 · Chapter 3 · Construction and Workmanship

Regulation 99. Cross tubes

Official text — not yet verifiedGazette 1 Oct 2026 · printed pp. 565–566Figure referenced

Not yet checked against the official Gazette; verify before relying on it.

Reproduced from the Gazette of India · verification status above

99. Cross tubes.─ (1) Cross tubes shall be made from seamless steel pipes or from plate or strip rolled and electric resistance or fusion butt welded into pipes by electric arc process. The fusion welding shall conform to the requirements of Chapter-12. Tolerances on these pipes shall conform to the requirements of regulation 251. Where welded pipes are used, the longitudinal welds shall be so situated that they are not exposed to the direct impact of flame.

(2)Cross tubes shall not exceed 305 mm internal diameter. The minimum thickness shall be 8 mm.

(3)Where welded construction is employed, the tubes shall be of sufficient length to enter the furnace plate and the flush with the water side all round or project not less than 6 mm and not more than 16 mm into the water space at any part of the circumference. Where the tubes are fusion welded in position, the firebox plates shall be suitably chamfered and the joints shall be welded externally and internally (see

Fig. 3/5).

Fig. 3/5: Fusion Welding of Cross Tubes of Vertical Cross Tube Boilers

Referenced provisions

Reg. 251

Figures cited in this regulation (1, exact crops of the Gazette)

Gazette Fig. 3/5: Fusion Welding of Cross Tubes of Vertical Cross Tube Boilers
Fig. 3/5Fusion Welding of Cross Tubes of Vertical Cross Tube Boilers
View Gazette page 566 · figure catalogue
Reconstructed CAD: DXF · SVG · Preview (redrawn, checked against the print; technical review pending)
Independent explanation — not the law · draft · engineer review in progress

In short

Regulation 99 sets the material, size and fitting rules for cross tubes in vertical cross tube boilers.

Key points

  • (1) Cross tubes are seamless steel pipe, or plate or strip rolled and electric resistance or fusion butt welded by electric arc. Fusion welding follows Chapter 12 and pipe tolerances follow regulation 251. Longitudinal welds must not face direct flame impact.
  • (2) Maximum internal diameter 305 mm, minimum thickness 8 mm.
  • (3) In welded construction, the tube enters the furnace plate and is flush with the water side, or projects not less than 6 mm and not more than 16 mm into the water space. Where tubes are fusion welded, firebox plates are chamfered and joints welded inside and outside (Fig. 3/5).

Written by IBRsource editors · last edited 2026-11-20. Explanations simplify and are not a design method, testing procedure or authorisation. Requirements come from the complete regulations, the Gazette and approved documentation.

Comparison pending: the IBR 1950 text in force on 30 September 2026 is not yet established for this provision, so no change is claimed (how this works).

Orientation hints (unverified)

These candidates come from automated heading matching against DPIIT's scanned historical print edition of IBR 1950. That edition uses imperial units and riveted-construction provisions, so it is not the operative 2026 predecessor text. Regulation numbers alone never prove equivalence.

Historical 1950-edition reg.Heading as OCR'dHeading similaritySource image
227Cross Tubes100%Chapter IV (DPIIT scan), image 15
631Tubes100%Chapter XV (DPIIT scan), image 3
IBR 1950 regulation 227 as last published in the DPIIT web edition (archived 2022)

Unofficial archived copy, not verified; see the regulation 227 page for its amendments.

Reg. 227, Reg. 228, Reg. 229

FURNACES

Cross Tubes

The working pressure of the tubes shall be determined by the following formula :-
W. P. = 200 (t - 7)
Eqn.(64)
D

where
W. P. = working pressure in lbs. per sq. inch.

t = minimum thickness in 32nds of an inch.

D = the internal diameter in inches of the cross tube.

Reg. 228

FURNACES

Uptakes of Vertical Boilers

The working pressure for uptake tube of vertical boilers shall be determined by Eqns. 57 and 58 but only half the least pressure so found is to be allowed for uptake tubes.

Reg. 229

SUPPORTS FOR COMBUSTION CHAMBER AND FIREBOX CROWN

Girder stay for firebox crowns

a) For girders supporting crown plates of rectangular fireboxes, where the ends of the girders are supported by the vertical end or side plates, their proportions shall be calculated from the following formula : -
W. P. = CSTD2 Eqn.(65)
L2Y

where
W. P. = working pressure in lb. per sq. inch,

S = Minimum tensile stress of the material in tons per sq. inch,

T = Total thickness of the stay in thirty seconds of an inch,

D = Depth of the girder stay in inches,

L = Length of girder stay in inches measured between the inside of the tube plate and the firehole plate, or between the inside of the side plates, according to the method of support

Y = Pitch of girder stays in inches,

C = 22 for steel plates or steel forgings, 19 for steel castings.
b) Where girders are supported in any other way than by the end or side plates of the firebox or combustion chamber the calculations for determining the working pressure shall be made in accordance with the actual conditions of support.

In such cases the length of the strip of firebox or combustion chamber top plate to be supported by the girder shall, subject to the limit imposed on the distance of the nearest stay, be taken as equal to the product of the number of bolts carried by the girder into the pitch of the bolts. A maximum nominal stress of 14,000 lbs. per square inch on girder section shall be allowed for steel.

c) Slings, links pins, rivets and connections to shell of slung girders shall be sufficient to carry the whole load that would otherwise be carried by the girder, and each girder must be equally slug or supported. For stresses allowed on the sections, see Regulation 203.
d) In the case of girders supported at the ends only by angle bars riveted to casing crown, the length L may, when the girder extends over the full breadth of the angle face, be taken as the distance between the centres of the angle faces. When this distance does not exceed that of L in the formula, the pressure shall be determined in the ordinary way. The supporting angles and rivets shall be of sufficient section for the intended purpose. For stresses allowed on the sections, see Regulation 203.

Images of the official Gazette pages that contain this regulation. Click to zoom. Compare word by word before relying on the extracted text.

Instrument
Indian Boiler Regulations, 2026 (made by the Central Boilers Board under s.40 of the Boilers Act, 2025)
Notification
F.No. P-30014/3/2021-Boiler dated 7 Aug 2026
Published
Gazette of India, Extraordinary, Part III Sec. 4, No. 596, 1 Oct 2026 (CG-DL-E-06102026-276813)
In force
1 Oct 2026 (reg. 1(3): date of publication in the Official Gazette)
Printed Gazette page
565–566
PDF page index
565–566 · open official e-Gazette PDF
Extraction
pdftotext layout mode, sequential regulation detector · text hash f8f3304058567dfc
Verification
Official text — not yet verified
Amendments checked
None known after 1 Oct 2026 as of build date (not a guarantee). Amendment log
How to cite

Indian Boiler Regulations, 2026, reg. 99, Regulation 99, Gazette of India, Extraordinary, Part III—Section 4, No. 596, 1 October 2026, printed p.565–566. https://egazette.gov.in/WriteReadData/2026/276813.pdf (text consulted via IBRsource, 2026-11-23).

The citation refers to the government publication. Cite the Gazette, not this website.