Indian Boiler Regulations, 2026 · Chapter 3 · Construction and Workmanship

Regulation 111. Girder stays for firebox and combustion chamber crowns

Official text — not yet verifiedGazette 1 Oct 2026 · printed pp. 568–569Figure referenced

Not yet checked against the official Gazette; verify before relying on it.

Reproduced from the Gazette of India · verification status above

111. Girder stays for firebox and combustion chamber crowns.─ (1) Each girder when of the normal type, fitted with stay bolts and nuts, shall be of the double plate interconnected type of sufficient strength to support its proportion of the load on the crown to support plate independently of the crown plate, and the bolts or weld attachments shall have sufficient cross-sectional area to carry the applied load.

(2)The clear waterway between the crown plate and the underside of the girder bars shall be as large as practicable but in no case less than 38 mm as in Fig.3/8.

(3)The ends of the girders shall not rest on the landing of the flat crown plate but shall be carefully fitted to bed directly on the bends of the corners of the vertical end or side plates.

(4)The toes of the girder plates shall be solid with the girder plates and not separate pieces attached thereto.

(5)Girders shall be properly attached to the crown plate by bolts or screws.

(6)Where an all welded firebox is fitted, the girder stays may be welded to the firebox prior to stress relieving. The girder stays shall be recessed for waterways as in sub-regulation (2) (Fig. 3/6 and Fig. 3/7). Such girders shall be securely welded by an approved method to the firebox crown. The method of welding and the proportions of attachment shall be to be satisfaction of the Inspecting Authority.

Fig. 3/6 Fig. 3/7

Figures cited in this regulation (3, exact crops of the Gazette)

Gazette Fig. 3/6
Fig. 3/6(no caption printed with this figure)
View Gazette page 568 · figure catalogue
Auto-traced outline: SVG · DXF (not to scale, may copy print defects)
Gazette Fig. 3/7
Fig. 3/7(no caption printed with this figure)
View Gazette page 568 · figure catalogue
Auto-traced outline: SVG · DXF (not to scale, may copy print defects)
Gazette Fig. 3/8
Fig. 3/8(no caption printed with this figure)
View Gazette page 569 · figure catalogue
Auto-traced outline: SVG · DXF (not to scale, may copy print defects)
Independent explanation — not the law · draft · engineer review in progress

In short

Regulation 111 sets the design and fitting rules for girder stays supporting firebox and combustion chamber crowns.

Key points

  • (1) Normal-type girders with stay bolts and nuts are double plate and interconnected. They must carry their share of the crown load independently of the crown plate, and the bolts or weld attachments must have enough area for the load.
  • (2) The clear waterway between the crown plate and the girder underside is as large as practicable, and never less than 38 mm (Fig. 3/8).
  • (3) Girder ends bed directly on the corner bends of the end or side plates.
  • (4) Girder toes are solid with the girder plates, not separate pieces.
  • (5) Girders are attached to the crown plate by bolts or screws.
  • (6) In an all-welded firebox, girder stays may be welded to the crown before stress relieving. They are recessed for waterways (Figs. 3/6 and 3/7). The welding method and attachment proportions must satisfy the Inspecting Authority.

Watch out

  • Girder ends must not rest on the landing of the flat crown plate.

Written by IBRsource editors · last edited 2026-11-20. Explanations simplify and are not a design method, testing procedure or authorisation. Requirements come from the complete regulations, the Gazette and approved documentation.

Comparison pending: the IBR 1950 text in force on 30 September 2026 is not yet established for this provision, so no change is claimed (how this works).

Orientation hints (unverified)

These candidates come from automated heading matching against DPIIT's scanned historical print edition of IBR 1950. That edition uses imperial units and riveted-construction provisions, so it is not the operative 2026 predecessor text. Regulation numbers alone never prove equivalence.

No candidate heading found in the historical print edition.

Images of the official Gazette pages that contain this regulation. Click to zoom. Compare word by word before relying on the extracted text.

Instrument
Indian Boiler Regulations, 2026 (made by the Central Boilers Board under s.40 of the Boilers Act, 2025)
Notification
F.No. P-30014/3/2021-Boiler dated 7 Aug 2026
Published
Gazette of India, Extraordinary, Part III Sec. 4, No. 596, 1 Oct 2026 (CG-DL-E-06102026-276813)
In force
1 Oct 2026 (reg. 1(3): date of publication in the Official Gazette)
Printed Gazette page
568–569
PDF page index
568–569 · open official e-Gazette PDF
Extraction
pdftotext layout mode, sequential regulation detector · text hash a3ad6dfca80015b7
Verification
Official text — not yet verified
Amendments checked
None known after 1 Oct 2026 as of build date (not a guarantee). Amendment log
How to cite

Indian Boiler Regulations, 2026, reg. 111, Regulation 111, Gazette of India, Extraordinary, Part III—Section 4, No. 596, 1 October 2026, printed p.568–569. https://egazette.gov.in/WriteReadData/2026/276813.pdf (text consulted via IBRsource, 2026-11-23).

The citation refers to the government publication. Cite the Gazette, not this website.