141. Compensation for cutting large holes in shell type boilers.─ Where holes are cut in the cylindrical shell for the purpose of attaching a seating of frame or door, compensation shall be provided such that the added sectional area, including parts of the frame within 101.6 mm of the shell shall be not less than the sectional area of the plate removed which shall be the product of the diameter of the opening and the calculated thickness of the plate as found by Equation(4/2). Where holes are cut in the cylindrical shell for the purpose of fixing seating for mountings and the diameter of the holes is greater than 2¼ times thickness of the shell plate plus 70 mm, compensation shall be provided. Where a large opening is cut in a cylindrical shell to receive another part of the structure, the sides where cut away shall be efficiently cross-stayed or strengthened in some other effective manner.
Tables and formulae are shown in their extracted layout. Alignment, superscripts and subscripts may be lost. The Gazette page image is authoritative.
In short
Regulation 141 requires compensation when large holes are cut in the cylindrical shell of shell type boilers.
Key points
- Holes for a seating, frame or door: compensation must add area (counting frame parts within 101.6 mm of the shell) that is at least the sectional area of plate removed. That area = opening diameter × calculated plate thickness from Equation (4/2).
- Holes for mounting seatings: compensation is needed where the hole diameter exceeds 2¼ times the shell plate thickness plus 70 mm.
- Where a large opening receives another part of the structure, the cut sides must be efficiently cross-stayed or strengthened in another effective way.
Written by IBRsource editors · last edited 2026-11-20. Explanations simplify and are not a design method, testing procedure or authorisation. Requirements come from the complete regulations, the Gazette and approved documentation.
Comparison pending: the IBR 1950 text in force on 30 September 2026 is not yet established for this provision, so no change is claimed (how this works).
Orientation hints (unverified)
These candidates come from automated heading matching against DPIIT's scanned historical print edition of IBR 1950. That edition uses imperial units and riveted-construction provisions, so it is not the operative 2026 predecessor text. Regulation numbers alone never prove equivalence.
No candidate heading found in the historical print edition.
Images of the official Gazette pages that contain this regulation. Click to zoom. Compare word by word before relying on the extracted text.


Indian Boiler Regulations, 2026, reg. 141, Regulation 141, Gazette of India, Extraordinary, Part III—Section 4, No. 596, 1 October 2026, printed p.585–586. https://egazette.gov.in/WriteReadData/2026/276813.pdf (text consulted via IBRsource, 2026-11-23).
The citation refers to the government publication. Cite the Gazette, not this website.