Indian Boiler Regulations, 2026 · Chapter 8 · Inspection and Testing of Boilers and Pipes during Construction and Boiler Registration
Regulation 318. Procedure for welding during repairs
Not yet checked against the official Gazette; verify before relying on it.
318. Procedure for welding during repairs. The repairer shall satisfy the inspecting Authority :-
(1)That the electric arc or oxy-acetylene welding sets and all other tools and plant in his possession for carrying out repairs are suitable for the work undertaken.
(2)That the quality of material used conforms to the specification that are prescribed.
(3)That the supervisory and operational staff employed by him possess the necessary training and experience for the work under taken.
(4)That all welders employed by him possess certificates issued as required under Chapter-13 of these Regulations.
(5)Standard of work shall be of high order and comply with all the requirements and test that may be prescribed by the Chief Inspector.
In short
Before welding during repairs, the repairer must satisfy the Inspecting Authority that:
- (1) the electric arc or oxy-acetylene welding sets and other tools and plant are suitable for the work;
- (2) the material conforms to the prescribed specifications;
- (3) supervisory and operational staff have the necessary training and experience;
- (4) all welders hold certificates issued under Chapter-13; and
- (5) the work is of a high standard and meets the requirements and tests the Chief Inspector prescribes.
Written by IBRsource editors · last edited 2026-11-20. Explanations simplify and are not a design method, testing procedure or authorisation. Requirements come from the complete regulations, the Gazette and approved documentation.
Comparison pending: the IBR 1950 text in force on 30 September 2026 is not yet established for this provision, so no change is claimed (how this works).
Orientation hints (unverified)
These candidates come from automated heading matching against DPIIT's scanned historical print edition of IBR 1950. That edition uses imperial units and riveted-construction provisions, so it is not the operative 2026 predecessor text. Regulation numbers alone never prove equivalence.
| Historical 1950-edition reg. | Heading as OCR'd | Heading similarity | Source image |
|---|---|---|---|
| 8 | Welding | 100% | Chapter I (DPIIT scan), image 3 |
Amendment history of the candidate IBR 1950 regulation: Reg. 8 (2 amendments)
IBR 1950 regulation 8 as last published in the DPIIT web edition (archived 2022)
Unofficial archived copy, not verified; see the regulation 8 page for its amendments.
| Reg. 8 Welding:- |
| (a) The use of welding in the construction of boilers shall be permitted only where specifically provided for in the standard conditions. |
Images of the official Gazette pages that contain this regulation. Click to zoom. Compare word by word before relying on the extracted text.

Indian Boiler Regulations, 2026, reg. 318, Regulation 318, Gazette of India, Extraordinary, Part III—Section 4, No. 596, 1 October 2026, printed p.720. https://egazette.gov.in/WriteReadData/2026/276813.pdf (text consulted via IBRsource, 2026-11-23).
The citation refers to the government publication. Cite the Gazette, not this website.