Regulation 313. Ageing of shell type boilers
Not yet checked against the official Gazette; verify before relying on it.
313. Ageing of shell type boilers.─(1) In order to take the ageing effect on boilers, the design pressure as calculated from the formulae in these regulations shall be reduced as per the table given below:
| TABLE | 8/4 | |||||||||
| Age of boiler exceeding (in years) | 25 | 35 | 45 | 50 | 60 | 70 | 80 | 90 | 100 | |
| Design Pressure (Percentage) | 95 | 90 | 85 | 80 | 70 | 60 | 50 | 40 | 30 | |
Table structure read from the Gazette PDF, page 712. Verification status as for the text above.
Show original extracted text (diagnostic, not authoritative)
Age of boiler exceeding (in years) TABLE 8/4
Design Pressure (Percentage) 25 35 45 50 60 70 80 90 100
95 90 85 80 70 60 50 40 30(2)For those boilers, the plates of which have already been cut and tested shall be given a further lease of life of fifty years from the date of the test of the boilers. The design pressure that shall be allowed after the testing shall be reduced as per the table given below:
TABLE 8/5
| TABLE 8/5 | ||||||
| Period after date of test (in years) | 10 | 20 | 30 | 40 | 50 | |
| Design pressure allowed (percentage) | 90 | 80 | 70 | 50 | 30 |
Table structure read from the Gazette PDF, page 712. Verification status as for the text above.
Show original extracted text (diagnostic, not authoritative)
Period after date of test (in years) 10 20 30 40 50 Design pressure allowed (percentage)
90 80 70 50 30
(3)(a)Shell type Waste Heat Boilers(un-fired), on completion of a life of twenty-five years, shall be non-destructively tested by a Remnant Life Assessment Organization (RLAO) approved by Central Boilers Board.
(b)Pressure parts, such as shell, end- plates, stand pipes etc., of such boilers, shall be inspected by Ultrasonic testing, Magnetic particle testing and Dye Penetrant testing.
(c)If results are acceptable as per the standards laid down by the Central Boilers Board, a certificate shall be issued by the Chief Inspector or Director of Boilers as the case may be, for extending the life of the boiler for a further period of twelve years or such less period as recommended by the Remnant Life Assessment Organisation.
(d)The working pressure of such boilers may be reduced on the recommendation of the Remnant Life Assessment Organisation.
(e)The assessment or remnant life by non-destructive testing shall be carried out thereafter every twelve years by a Remnant Life Assessment Organisation (RLAO) approved by the Central Boilers Board. Such agency shall work in close coordination with the office of the Chief inspector or Director of Boilers as the case may be.
Note:
(1)It shall be at the option of the owner to opt for the provisions of sub-regulation (1) or sub-regulation (2) above or opt for the Remnant Life Assessment of boiler as per sub-regulation(3).
(2)Wherever, it is not possible to carry out non-destructively testing of boiler for Remnant Life Assessment, provisions of sub-regulation (1) or sub-regulation (2) shall be applicable.
Tables and formulae are shown in their extracted layout. Alignment, superscripts and subscripts may be lost. The Gazette page image is authoritative.
In short
Regulation 313 reduces the allowable design pressure of shell type boilers as they age, and gives owners an alternative: remnant life assessment.
Key points
- (1) Table 8/4 reduces the design pressure, calculated from the formulae in these regulations, to a percentage that falls as the boiler's age in years increases. See the Official text tab for the age bands and percentages.
- (2) Boilers whose plates have already been cut and tested get a further life of fifty years from the date of the test. The design pressure after testing is reduced as per Table 8/5.
- (3)(a) Un-fired shell type waste heat boilers must be non-destructively tested by a Remnant Life Assessment Organisation (RLAO) approved by the Central Boilers Board after twenty-five years.
- (3)(b) Pressure parts such as shell, end plates and stand pipes are inspected by ultrasonic, magnetic particle and dye penetrant testing.
- (3)(c) If results meet the Central Boilers Board's standards, the Chief Inspector or Director of Boilers issues a certificate extending life by twelve years, or less if the RLAO recommends.
- (3)(d) Working pressure may be reduced on the RLAO's recommendation.
- (3)(e) Assessment is then repeated every twelve years.
Watch out
- The owner may choose sub-regulation (1), sub-regulation (2), or remnant life assessment under sub-regulation (3).
- Where non-destructive testing for remnant life assessment is not possible, sub-regulation (1) or (2) applies.
Written by IBRsource editors · last edited 2026-11-20. Explanations simplify and are not a design method, testing procedure or authorisation. Requirements come from the complete regulations, the Gazette and approved documentation.
Comparison pending: the IBR 1950 text in force on 30 September 2026 is not yet established for this provision, so no change is claimed (how this works).
Orientation hints (unverified)
These candidates come from automated heading matching against DPIIT's scanned historical print edition of IBR 1950. That edition uses imperial units and riveted-construction provisions, so it is not the operative 2026 predecessor text. Regulation numbers alone never prove equivalence.
No candidate heading found in the historical print edition.
Images of the official Gazette pages that contain this regulation. Click to zoom. Compare word by word before relying on the extracted text.

Indian Boiler Regulations, 2026, reg. 313, Regulation 313, Gazette of India, Extraordinary, Part III—Section 4, No. 596, 1 October 2026, printed p.712. https://egazette.gov.in/WriteReadData/2026/276813.pdf (text consulted via IBRsource, 2026-11-23).
The citation refers to the government publication. Cite the Gazette, not this website.