Indian Boiler Regulations, 2026 · Chapter 8 · Inspection and Testing of Boilers and Pipes during Construction and Boiler Registration

Regulation 301. Engraving of registry number

Official text — not yet verifiedGazette 1 Oct 2026 · printed pp. 701–702Table

Not yet checked against the official Gazette; verify before relying on it.

Reproduced from the Gazette of India · verification status above

301. Engraving of registry number.─ (1) (a) (i) The registry number of every boiler shall, within a period of one month from the date of receipt thereof, shall be cut in the front plate or any such position as shall be pointed out by the Inspector.

(ii)The device for each State or Union territory shall be distinguished by the following letters as mentioned in the

Table below, namely:-

Serial Table Letters

Serial No.Name of State/Union territoryLetters
(1)(2)(3)
1.Andaman and Nicobar IslandsA&N
2.Andhra PradeshAP
3.Arunachal PradeshARP
4.AssamA
5.BiharBR
6.ChhattisgarhCG
7.Dadra and Nagar HaveliDNH
8.DelhiD
9.GoaG
10.GujaratGT
11.HaryanaHA
12.Himachal PradeshHP
13.Jammu & KashmirJK
14.JharkhandJH
15.KarnatakaKTK
16.KeralaK
17.Laccadive, Minicoy & Amindivi IslandsLI
18.LadakhLA
19.Madhya PradeshMP
20.MaharashtraMR
21.ManipurMA
22.MeghalayaML
23.NagalandNL
24.OrissaOR
25.PondicherryPY
26.PunjabPI
27.RajasthanRI
28.Tamil NaduT
29.TelanganaTG
30.TripuraTR
31.Uttar PradeshUP
32.UttrakhandUR
33.West BengalWBL

Table structure read from the Gazette PDF, pages 701, 702. Verification status as for the text above.

Show original extracted text (diagnostic, not authoritative)
No.                Name of State/Union territory
                                                                      (3)
   (1)                                     (2)                 A&N
     1.            Andaman and Nicobar Islands                 AP
     2.            Andhra Pradesh                              ARP
     3.            Arunachal Pradesh                           A
     4.            Assam                                       BR
     5.            Bihar                                       CG
     6.            Chhattisgarh                                DNH
     7.            Dadra and Nagar Haveli                      D
     8.            Delhi                                       G
     9.            Goa                                         GT
     10.           Gujarat                                     HA
     11.           Haryana                                     HP
     12.           Himachal Pradesh                            JK
     13.           Jammu & Kashmir


     14. Jharkhand                              JH
     15. Karnataka                              KTK
     16. Kerala                                 K
     17. Laccadive, Minicoy & Amindivi Islands  LI
     18. Ladakh                                 LA
     19. Madhya Pradesh                         MP
     20. Maharashtra                            MR
     21. Manipur                                MA
     22. Meghalaya                              ML
     23. Nagaland                               NL
     24. Orissa                                 OR
     25. Pondicherry                            PY
     26. Punjab                                 PI
     27. Rajasthan                              RI
     28. Tamil Nadu                             T
     29. Telangana                              TG
     30. Tripura                                TR
     31. Uttar Pradesh                          UP
     32. Uttrakhand                             UR
     33. West Bengal                            WBL

(b)(i) The distinguishing letters shall be engraved above a number and separated there from by a horizontal line 64 mm in length.

(ii)The letters and figures shall be 25 mm in height and of suitable breadth, provided that in the case of small boilers the letters and figures of the device may, in the discretion of the Chief Inspector, be reduced to 10 mm in height. The whole shall be enclosed in a rectangle, the upper and lower sides of which shall be 76 mm apart and 6 mm clear of the top of the letters and the bottom of the figures respectively as indicated below:

Example:-

MR
1234

(c)In the case of registration of small industrial boilers, the letter “S” shall be added as a prefixed to the registration number below the distinguishing letters for State or Union territories as indicated below: -

Example:-

UP
S- ----

(d)The side lines shall be at equal distance clear from the figures and the engraving shall not be less than

0.4 mm in depth.

(2)The engraving shall be complete and ready for verification within one month from the date of receipt of registry number, and the fact shall be reported to the Chief Inspector of Boiler within this period.

(3)(a) Boilers having registry devices differing from those prescribed herein shall have such devices altered or crossed out and engraved a new one in conformity with those prescribed above.

(b)The original numbers of such boilers shall be retained in the new device, provided that in the case of boilers which were registered in a State or Union territory which has since become extinct, a new number shall be given by the State or Union territory where the Boiler is operating and any number once allotted to a boiler shall not be used again for another boiler.

Tables and formulae are shown in their extracted layout. Alignment, superscripts and subscripts may be lost. The Gazette page image is authoritative.

Independent explanation — not the law · draft · engineer review in progress

In short

Regulation 301 sets how the registry number allotted to a boiler must be engraved on it: where, how large, in what layout, and how quickly.

Key points

  • (1)(a) The registry number must be cut in the front plate, or in another position pointed out by the Inspector, within one month from the date it is received. Each State or Union territory has its own distinguishing letters, listed in the table (for example "MR" for Maharashtra, "UP" for Uttar Pradesh). See the Official text tab for the full list.
  • (1)(b) The letters go above the number, separated by a horizontal line 64 mm long. Letters and figures are 25 mm high. The whole device is enclosed in a rectangle whose upper and lower sides are 76 mm apart and 6 mm clear of the letters and figures.
  • (1)(c) For small industrial boilers, the letter "S" is prefixed to the registration number, below the State or Union territory letters.
  • (1)(d) The side lines must be equally clear of the figures, and the engraving must be at least 0.4 mm deep.
  • (2) The engraving must be complete and ready for verification within one month of receiving the registry number, and this must be reported to the Chief Inspector within the same period.
  • (3) Boilers carrying a registry device that differs from this pattern must have it altered or crossed out and a new one engraved. The original number is kept in the new device.

Watch out

  • For small boilers, the Chief Inspector may allow the letters and figures to be reduced to 10 mm in height. This is at the Chief Inspector's discretion.
  • If the boiler was registered in a State or Union territory that no longer exists, the State or Union territory where it now operates gives a new number. A number once allotted is never reused for another boiler.

Written by IBRsource editors · last edited 2026-11-20. Explanations simplify and are not a design method, testing procedure or authorisation. Requirements come from the complete regulations, the Gazette and approved documentation.

Comparison pending: the IBR 1950 text in force on 30 September 2026 is not yet established for this provision, so no change is claimed (how this works).

Orientation hints (unverified)

These candidates come from automated heading matching against DPIIT's scanned historical print edition of IBR 1950. That edition uses imperial units and riveted-construction provisions, so it is not the operative 2026 predecessor text. Regulation numbers alone never prove equivalence.

Historical 1950-edition reg.Heading as OCR'dHeading similaritySource image
534Engraving of Registry number100%Chapter XI (DPIIT scan), image 9
IBR 1950 regulation 534 as last published in the DPIIT web edition (archived 2022)

Unofficial archived copy, not verified; see the regulation 534 page for its amendments.


Reg. 534
, Reg. 534 A, Reg. 534 B
STANDARD CONDITIONS FOR THE DESIGN AND CONSTRUCTION OF ECONOMISER, FEED PIPES, FEED HEATERS AND OTHER SIMILAR VESSELS

REGULATIONS FOR REGISTRATION AND INSPECTION OF ECONOMISERS AND FEED PIPES

Engraving of registry number

a)

Every economiser shall have a plate with its registry number engraved, secured in a conspicuous place and wherever practicable stamped for identification with that number in a prominent place.
b) A letter “E” shall be refixed to the registry number in the denominator of the appropriate device as shown in Regulation 382.

Example:-
UP
E-53


Reg. 534 A

STANDARD CONDITIONS FOR THE DESIGN AND CONSTRUCTION OF ECONOMISER, FEED PIPES, FEED HEATERS AND OTHER SIMILAR VESSELS

REGULATIONS FOR REGISTRATION AND INSPECTION OF ECONOMISERS AND FEED PIPES

Inspection of Feed Pipes

a)

Feed pipes shall be inspected and hydraulically tested before erection in place, and the hydraulic test pressure shall be not less than twice the working pressure of the economiser. A certificate from the recognized maker or Inspecting Authority that this has been done may be accepted. If the Inspector is satisfied with the test, the pipes may be erected. No separate certificate for feed pipes shall be issued, nor shall a separate fee be charged for their inspection. The engraving shall be done within a period of two months from the date of receipt of the registry number.
b) At subsequent inspection or at any other time, the Inspector may make an external Inspection of feed pipes and if found in any unsatisfactory condition he shall report the matter to the Chief Inspector who may require the pipes to be hydraulically tested.
c) The engraving shall be completed and ready for verification within  thirty days from the date of receipt of the engraving slip from the Chief Inspector of the State.
d) Economisers having registry devices different  from those prescribed in clause (a) and (b) shall have such devices crossed out or erased  and engraved a new in conformity with those prescribed in the clauses aforesaid.  The original numbers of such economisers shall be retained in the new device provided that incase of economisers operating in an area which consequent upon the reorganisation of state forms part of another state, new numbers shall be given by the Chief Inspector of the State.  A number once allotted shall not be used again in another economiser. 


Reg. 534 B

STANDARD CONDITIONS FOR THE DESIGN AND CONSTRUCTION OF ECONOMISER, FEED PIPES, FEED HEATERS AND OTHER SIMILAR VESSELS

REGULATIONS FOR REGISTRATION AND INSPECTION OF ECONOMISERS AND FEED PIPES

Submission of plans of Feed Pipes
a) The fees for the scrutiny of plans and particulars of the material, design and construction of feed pipes, before commencement of manufacture of the feed pipes shall be at the rate of Rs. 30 for 30 metres of piping or part thereof, subject to a minimum of Rs. 50, inclusive of all fittings excepting fittings like feed water heaters. For any such fittings like feed water heater, the fee shall be equal to the registration fee of the boiler to which feed pipe is attached subject to a maximum of Rs.1500.
b) The fees for scrutiny of lay-out plans of feed pipes shall be Rs. 20 for 30 metres of piping or part thereof, subject to a minimum of Rs.50, exclusive of fittings like feed water heater for any such fittings like feed water heater, the fee shall be Rs. 150.00 for each such fittings.”.

Images of the official Gazette pages that contain this regulation. Click to zoom. Compare word by word before relying on the extracted text.

Instrument
Indian Boiler Regulations, 2026 (made by the Central Boilers Board under s.40 of the Boilers Act, 2025)
Notification
F.No. P-30014/3/2021-Boiler dated 7 Aug 2026
Published
Gazette of India, Extraordinary, Part III Sec. 4, No. 596, 1 Oct 2026 (CG-DL-E-06102026-276813)
In force
1 Oct 2026 (reg. 1(3): date of publication in the Official Gazette)
Printed Gazette page
701–702
PDF page index
701–702 · open official e-Gazette PDF
Extraction
pdftotext layout mode, sequential regulation detector · text hash 653415df69141e8a
Verification
Official text — not yet verified
Amendments checked
None known after 1 Oct 2026 as of build date (not a guarantee). Amendment log
How to cite

Indian Boiler Regulations, 2026, reg. 301, Regulation 301, Gazette of India, Extraordinary, Part III—Section 4, No. 596, 1 October 2026, printed p.701–702. https://egazette.gov.in/WriteReadData/2026/276813.pdf (text consulted via IBRsource, 2026-11-23).