Indian Boiler Regulations, 2026 · Chapter 8 · Inspection and Testing of Boilers and Pipes during Construction and Boiler Registration

Regulation 308. Maintenance of records

Official text — not yet verifiedGazette 1 Oct 2026 · printed p. 707

Not yet checked against the official Gazette; verify before relying on it.

Reproduced from the Gazette of India · verification status above

308. Maintenance of records.─ (1) The Inspecting Authority shall maintain the records pertaining to the boiler or the economiser, as the case may be, including all the certificates provided in Form-I(Part-B), Form-I(Part-C),Form-IV(Part-A), Form-IV(Part-B), Form-IV(Part-C), Form-IV(Part-D), Form-V(Part-A) and Form-XVI and the copies of the approved drawings for a period of at least three years after registration of the boiler and thereafter these records may be sent to the owner of the boiler by the Inspecting Authority.

(2)The owner of a boiler or economiser shall maintain the records pertaining to the boiler or economiser as the case may be, including the certificates provided in Form-I(Part-B), Form-I(Part-C), Form-IV(Part-B), Form-IV(Part-C), Form-V(Part-A), and Form-XV and the copies of the approved drawing for the entire life of the boiler or economiser as the case may be.

(3)In the event of any transfer of the ownership, the records mentioned above shall be transferred to the new owner and the new owner will maintain the record in accordance with the provision of sub-regulation (2) above.

(4)The manufacturer of boiler or economiser or steam pipe shall maintain the record pertaining to the boiler or economiser or steam pipe, as the case may be, including the certificates provided in Form-I(Part-B), Form-I(Part-C), Form-IV(Part-B), Form-IV(Part-C), Form-IV(Part-D), Form-V(Part-A), Form-V(Part-B) , Form-XV, and Form-XVI and the copies of the approved drawings for a period of at least five years.

Independent explanation — not the law · draft · engineer review in progress

In short

Regulation 308 says who must keep a boiler's or economiser's records, which certificates and drawings are included, and for how long.

Key points

  • (1) Inspecting Authority: keeps the records, including the certificates in Form-I (Part-B and Part-C), Form-IV (Part-A to Part-D), Form-V (Part-A) and Form-XVI, and copies of approved drawings, for at least three years after registration. After that it may send them to the owner.
  • (2) Owner: keeps the records, including the certificates in Form-I (Part-B and Part-C), Form-IV (Part-B and Part-C), Form-V (Part-A) and Form-XV, and copies of approved drawings, for the entire life of the boiler or economiser.
  • (3) Change of ownership: the records pass to the new owner, who must keep them as in sub-regulation (2).
  • (4) Manufacturer of a boiler, economiser or steam pipe: keeps the records, including the certificates in Form-I (Part-B and Part-C), Form-IV (Part-B to Part-D), Form-V (Part-A and Part-B), Form-XV and Form-XVI, and copies of approved drawings, for at least five years.

Watch out

  • The list of forms differs for each party. Check the exact list that applies to you in the Official text tab.

Written by IBRsource editors · last edited 2026-11-20. Explanations simplify and are not a design method, testing procedure or authorisation. Requirements come from the complete regulations, the Gazette and approved documentation.

Comparison pending: the IBR 1950 text in force on 30 September 2026 is not yet established for this provision, so no change is claimed (how this works).

Orientation hints (unverified)

These candidates come from automated heading matching against DPIIT's scanned historical print edition of IBR 1950. That edition uses imperial units and riveted-construction provisions, so it is not the operative 2026 predecessor text. Regulation numbers alone never prove equivalence.

No candidate heading found in the historical print edition.

Images of the official Gazette pages that contain this regulation. Click to zoom. Compare word by word before relying on the extracted text.

Instrument
Indian Boiler Regulations, 2026 (made by the Central Boilers Board under s.40 of the Boilers Act, 2025)
Notification
F.No. P-30014/3/2021-Boiler dated 7 Aug 2026
Published
Gazette of India, Extraordinary, Part III Sec. 4, No. 596, 1 Oct 2026 (CG-DL-E-06102026-276813)
In force
1 Oct 2026 (reg. 1(3): date of publication in the Official Gazette)
Printed Gazette page
707
PDF page index
707 · open official e-Gazette PDF
Extraction
pdftotext layout mode, sequential regulation detector · text hash 23f20acf0f138ba1
Verification
Official text — not yet verified
Amendments checked
None known after 1 Oct 2026 as of build date (not a guarantee). Amendment log
How to cite

Indian Boiler Regulations, 2026, reg. 308, Regulation 308, Gazette of India, Extraordinary, Part III—Section 4, No. 596, 1 October 2026, printed p.707. https://egazette.gov.in/WriteReadData/2026/276813.pdf (text consulted via IBRsource, 2026-11-23).

The citation refers to the government publication. Cite the Gazette, not this website.

Help improve this page

Engineers like you keep IBRsource accurate. Every checked correction or tip helps the next reader.