Indian Boiler Regulations, 2026 · Chapter 7 · Pipes and Fittings

Regulation 255. Steam pipes and fittings

Official text — not yet verifiedGazette 1 Oct 2026 · printed pp. 651–652Table

Not yet checked against the official Gazette; verify before relying on it.

Reproduced from the Gazette of India · verification status above

255. Steam pipes and fittings.─ The pressure and temperature limits within which pipes, tees, branches, etc., are to be used, shall be in accordance with Table 7/4as given below:

Table 7/4: Maximum allowable working pressure and temperature

Serial NumberMaterial group as per Regulation 8Method of manufactureMaximum allowable working pressureMaximum permissible temperatureProduct Form
°C
(1)(2)(3)(4)(5)(6)
1.M1/Gr1,
M1/Gr2
Cold drawn seamlessNo restrictionAs per Table 2/1 of
Regulation 30
Straight,
bends or
fittings
2.Hot finished seamlessNo restrictionAs per Table 2/1 of
Regulation 30
-do-
3.Butt welded [Max. nominal bore
allowable 102mm]
21 kg/cm2 (g)260-do-
4.Electric Resistance weldedNo restrictionAs per Table 2/1 of
Regulation 30
-do-
5.Cast SteelCastingsNo restriction454-do-
6.M3/Gr1,
M3/Gr2,
M4/Gr1
Cold drawn seamless and
Castings
No restrictionAs per Table 2/1 of
Regulation 30
-do-
7.M5A/Gr1Cold drawn seamless and hot
finished seamless
No restrictionAs per Table 2/1 of
Regulation 30
-do-

Table structure read from the Gazette PDF, page 652. Verification status as for the text above.

Show original extracted text (diagnostic, not authoritative)
Serial         Material group  Method of manufacture               Maximum         Maximum                       Product
Number         as per                                              allowable       permissible                   Form
               Regulation 8                       (3)              working         temperature
      (1)                      Cold drawn seamless                 pressure                                           (6)
        1.             (2)                                                                   °C                  Straight,
                    M1/Gr1,                                               (4)                (5)                 bends or
        2.          M1/Gr2                                         No restriction  As per Table 2/1 of           fittings
                                                                                   Regulation 30                 -do-
        3.                     Hot finished seamless               No restriction
        4.                                                                         As per Table 2/1 of
                                                                                   Regulation 30
        5.
        6.                     Butt welded [Max. nominal bore      21 kg/cm2 (g) 260                             -do-
                               allowable 102mm]
        7.                     Electric Resistance welded          No restriction  As per Table 2/1 of -do-
                                                                                   Regulation 30

               Cast Steel      Castings                            No restriction  454                           -do-
               M3/Gr1,         Cold drawn seamless and             No restriction
               M3/Gr2,         Castings                                            As per Table 2/1 of -do-
               M4/Gr1
               M5A/Gr1         Cold drawn seamless and hot                         Regulation 30
                               finished seamless
                                                                   No restriction  As per Table 2/1 of -do-
                                                                                   Regulation 30

Parts of this extracted text look garbled; read the Gazette page before using any value.

Tables and formulae are shown in their extracted layout. Alignment, superscripts and subscripts may be lost. The Gazette page image is authoritative.

Referenced provisions

Reg. 3 · Reg. 8 · Reg. 30

Related calculators (on SteamCalc, a separate free site · general engineering calculation, not this regulation's own rule)

Steam pipe sizing by velocity · Steam pipe pressure drop

Independent explanation — not the law · draft · engineer review in progress

In short

The pressure and temperature limits for pipes, tees, branches and similar parts are set by Table 7/4. It is arranged by material group (the table heading says "as per Regulation 8", but the material groups are those of Table 2/1 in regulation 30), method of manufacture and product form.

Key points

  • Most combinations of material and manufacturing method have no pressure restriction in this table (the pressure still has to be justified by the design calculations), with temperature limited as per Table 2/1 of regulation 30.
  • Butt welded pipe is limited to 21 kg/cm2 (g) and 260 °C, with a maximum nominal bore of 102mm.
  • Cast steel castings have no pressure restriction but a temperature limit of 454 °C.

Watch out

  • The table layout is broken in the extracted text. Check the Gazette page for which material groups and methods sit on each row.

Written by IBRsource editors · last edited 2026-11-20. Explanations simplify and are not a design method, testing procedure or authorisation. Requirements come from the complete regulations, the Gazette and approved documentation.

Comparison pending: the IBR 1950 text in force on 30 September 2026 is not yet established for this provision, so no change is claimed (how this works).

Orientation hints (unverified)

These candidates come from automated heading matching against DPIIT's scanned historical print edition of IBR 1950. That edition uses imperial units and riveted-construction provisions, so it is not the operative 2026 predecessor text. Regulation numbers alone never prove equivalence.

No candidate heading found in the historical print edition.

Images of the official Gazette pages that contain this regulation. Click to zoom. Compare word by word before relying on the extracted text.

Instrument
Indian Boiler Regulations, 2026 (made by the Central Boilers Board under s.40 of the Boilers Act, 2025)
Notification
F.No. P-30014/3/2021-Boiler dated 7 Aug 2026
Published
Gazette of India, Extraordinary, Part III Sec. 4, No. 596, 1 Oct 2026 (CG-DL-E-06102026-276813)
In force
1 Oct 2026 (reg. 1(3): date of publication in the Official Gazette)
Printed Gazette page
651–652
PDF page index
651–652 · open official e-Gazette PDF
Extraction
pdftotext layout mode, sequential regulation detector · text hash 882881518e20b86a
Verification
Official text — not yet verified
Amendments checked
None known after 1 Oct 2026 as of build date (not a guarantee). Amendment log
How to cite

Indian Boiler Regulations, 2026, reg. 255, Regulation 255, Gazette of India, Extraordinary, Part III—Section 4, No. 596, 1 October 2026, printed p.651–652. https://egazette.gov.in/WriteReadData/2026/276813.pdf (text consulted via IBRsource, 2026-11-23).