Indian Boiler Regulations, 2026 · Chapter 7 · Pipes and Fittings
Regulation 284. Inspection during construction
Not yet checked against the official Gazette; verify before relying on it.
284.Inspection during construction.─ All parts of steam receivers, separators, catch waters and similar vessels shall be inspected at all appropriate stages of construction detailed in Appendix-A of these regulations.
In short
All parts of steam receivers, separators, catch waters and similar vessels must be inspected at all appropriate stages of construction, as detailed in Appendix-A.
Written by IBRsource editors · last edited 2026-11-20. Explanations simplify and are not a design method, testing procedure or authorisation. Requirements come from the complete regulations, the Gazette and approved documentation.
Comparison pending: the IBR 1950 text in force on 30 September 2026 is not yet established for this provision, so no change is claimed (how this works).
Orientation hints (unverified)
These candidates come from automated heading matching against DPIIT's scanned historical print edition of IBR 1950. That edition uses imperial units and riveted-construction provisions, so it is not the operative 2026 predecessor text. Regulation numbers alone never prove equivalence.
No candidate heading found in the historical print edition.
Images of the official Gazette pages that contain this regulation. Click to zoom. Compare word by word before relying on the extracted text.

Indian Boiler Regulations, 2026, reg. 284, Regulation 284, Gazette of India, Extraordinary, Part III—Section 4, No. 596, 1 October 2026, printed p.691. https://egazette.gov.in/WriteReadData/2026/276813.pdf (text consulted via IBRsource, 2026-11-23).
The citation refers to the government publication. Cite the Gazette, not this website.