Indian Boiler Regulations, 2026 · Chapter 1 · General Requirements, Registration, Recognition and Competent Persons
Regulation 3. General requirements, application of standard conditions and exception thereto
Not yet checked against the official Gazette; verify before relying on it.
3. General requirements, application of standard conditions and exception thereto.─
(1)No boiler shall be registered under sub-section (5) of section 12 of the Act and no certificate shall be issued under sub-section (6) of that section, unless the standard conditions in respect of material, design and construction, specified in these regulations are satisfied in respect of such a boiler.
(2)Notwithstanding anything contained in sub-regulation (1), the Chief Inspector may, subject to the provisions of regulation 29, register a boiler and issue a certificate authorising the use thereof, under any of the following circumstances, namely:-
(a)when the material used in the construction of a boiler, steam-pipe, economiser or superheater is not in conformity with these regulations but used in other countries as being suitable for use in the construction of boilers and steam-pipes, provided that such material is not specifically prohibited by these regulations and that the methods of manufacture, fabrication and heat treatment conform to the specified Codes or Standards;
(b)when the constructional features of a boiler, steam-pipe, economiser or superheater are not in conformity with these regulations but are not considered by the Board to be inferior in strength to those prescribed in these regulations and form part of the usual manufacturing practice of boilers and steam-pipes in other countries;
(c)when a boiler, steam-pipe, economiser or superheater has been built in conformity with these regulations but no certificate as required under the regulations is forthcoming;
(3)No structural part of a boiler which is subject to pressure, shall be made of Bessemer process steel or of Cast or Malleable Cast Iron.
(4)Where no specific provision is made in these regulations for design or manufacture of any pressure part, the Inspecting Authority may permit the design, manufacture, stage inspections and certification of such pressure parts including the valves; mountings and fittings conforming to the Codes or Standards like British Standards (BS), European Standards (EN), American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code, Tubular Exchanger Manufacturers Association (TEMA), Technical Requirements Document (TRD), GOsudarstvennyy Standrat(GOST) and Japanese Industrial Standards (JIS), which are known to be commonly used in industrially advanced countries and the decision of Inspecting Authorities shall be binding on all Registering Authorities.
(5)The tubes of boilers and heat exchangers made of titanium and other exotic metals may be approved as per international codes, including American Society of Mechanical Engineers (ASME), British Standards (BS), European Standards (EN), Deutsches Institut fur Normung(DIN), Tubular Exchanger Manufacturers Association (TEMA)with the minimum thickness specified in those codes of manufacture.
In short
Regulation 3 sets the basic rule. A boiler is registered, and its certificate issued, under s.12 of the Act only if the standard conditions in these regulations for material, design and construction are met.
The exceptions in sub-regulation (2)
Subject to regulation 29, the Chief Inspector may still register a boiler when:
- the material does not conform to these regulations but is used in other countries for boilers, is not specifically prohibited, and its manufacture, fabrication and heat treatment conform to the specified codes or standards;
- the constructional features differ from these regulations but are not considered by the Board to be weaker, and are usual manufacturing practice in other countries; or
- the boiler was built in conformity but the required certificate is not available.
Other points
- Pressure parts may not be made of Bessemer-process steel, cast iron or malleable cast iron (sub-reg. 3).
- Where the regulations have no specific provision for a pressure part, the Inspecting Authority may permit design, manufacture, stage inspection and certification to recognised international codes (BS, EN, ASME, TEMA, TRD, GOST, JIS). Its decision binds all Registering Authorities (sub-reg. 4).
- Titanium and other exotic-metal tubes may be approved to international codes with those codes' minimum thicknesses (sub-reg. 5).
These are discretionary powers of the authorities named. They do not give a manufacturer or owner an automatic right.
Written by IBRsource editors · last edited 2026-11-20. Explanations simplify and are not a design method, testing procedure or authorisation. Requirements come from the complete regulations, the Gazette and approved documentation.
Comparison pending: the IBR 1950 text in force on 30 September 2026 is not yet established for this provision, so no change is claimed (how this works).
Orientation hints (unverified)
These candidates come from automated heading matching against DPIIT's scanned historical print edition of IBR 1950. That edition uses imperial units and riveted-construction provisions, so it is not the operative 2026 predecessor text. Regulation numbers alone never prove equivalence.
| Historical 1950-edition reg. | Heading as OCR'd | Heading similarity | Source image |
|---|---|---|---|
| 52 | General | 100% | Chapter II (DPIIT scan), image 9 |
| 94 | General requirements | 100% | Chapter II (DPIIT scan), image 19 |
| 276 | General | 100% | Chapter V (DPIIT scan), image 11 |
Amendment history of the candidate IBR 1950 regulations: Reg. 52 (2 amendments)
IBR 1950 regulation 52 as last published in the DPIIT web edition (archived 2022)
Unofficial archived copy, not verified; see the regulation 52 page for its amendments.
| Reg. 52 MATERIALS OF CONSTRUCTION SEAMLESS FERRITIC PIPES FOR HIGH TEMPERATURE SERVICE |
| (i) These regulations cover both hot finished and cold drawn seamless pipes of ferritic alloy steel grades. These shall conform in all respects with the requirements herein specified. (ii) The seamless pipes conforming to other national/international standards which are known to be commonly used as being suitable for high temperature service can also be used with the designations of the national/international standards, provided such materials are not specifically prohibited by the regulations. (iii) While making pipes to other national/international standards the allowable stresses of the respective standard shall be strictly followed while designing the tubes. (iv) The design metal temperatures shall not exceed the following limits Grade Temp. Degree C (Degree F) P1, P2 537 (1000) P5, P9, P11, P12, P22, P91, X20CrMoV121 648 (1200) |
IBR 1950 regulation 94 as last published in the DPIIT web edition (archived 2019)
Unofficial archived copy, not verified; see the regulation 94 page for its amendments.
| Reg. 94 MATERIALS OF CONSTRUCTION COVERED ELECTRODES FOR METAL ARC WELDING OF MILD STEEL General requirements |
| (1) Application.- The following Regulations apply to electrodes of sizes 3/32 inch (12 S.W.G.) and larger in diameter for metal arc welding of carbon steels having ultimate tensile strength not exceeding 33 tons per square inch and Sulphur and Phosphorus contents not greater than 0.06 per cent each. Electrodes less than 3/32 inch in diameter shall not be used in boilers. The electrodes shall comply with the requirements of physical tests prescribed for each class. Their characteristics and behaviour under ordinary working conditions shall be such that satisfactory weld deposits can be made by a welder of average skill and experience and that the following characteristics are also obtained:-
(2) Classification.- The electrodes shall be classified into:
(3) Manufacture.- Electrodes may be made by any method that shall yield a product conforming to the requirements of these Regulations. (4) Size of Electrodes.- The nominal size of the electrodes shall refer to the diameter of the core wire and the length shall not exceed 18 inches. Provision shall be made for end or centre gripping. The tolerances on the specified diameter of the core wire of the electrodes shall be plus or minus 0.002 inch. (5) Covering.- The flux covering shall be sufficiently robust to withstand the normal conditions of transport, storage, handling and use, without damage and shall be uniform in thickness all over so that it fuses evenly. The variation in the thickness shall not exceed 3 per cent. (6) (a) Packing and storage.- Electrodes shall be suitably packed to guard against damage during transportation. When stored, the electrodes shall be kept in their original bundles or packings in a dry store room and under such conditions, the electrodes shall for a period of at least six months be capable of giving results similar to those which they would have given on the date of their despatch from the manufacturer. (b) Marking.- Each package shall be marked with the following information:-
(7) Tests.- The electrodes shall be subjected to Initial tests, Periodic check tests and Production control to ensure that the requirements of these Regulations are fulfilled. Electrodes intended for use with more than one type of current or polarity shall be tested using each type of current and polarity. Where any test specimen fails to satisfy the requirements of any particular test, two further test specimens shall be prepared using the electrodes from the same batch and submitted to the same test. The batch of electrodes shall be accepted as having passed the test provided that the tests of both the additional specimens are satisfactory. (8) Test Certificates.- The manufacturers shall, when called upon, produce the results of the most recent Periodic check tests carried out within the preceding 12 months, on electrodes representative of the electrodes supplied. |
IBR 1950 regulation 276 as last published in the DPIIT web edition (archived 2022)
Unofficial archived copy, not verified; see the regulation 276 page for its amendments.
|
| ||||||||||||||||||||||||||||||||
Reg. 277
| ||||||||||||||||||||||||||||||||
Images of the official Gazette pages that contain this regulation. Click to zoom. Compare word by word before relying on the extracted text.


Indian Boiler Regulations, 2026, reg. 3, Regulation 3, Gazette of India, Extraordinary, Part III—Section 4, No. 596, 1 October 2026, printed p.490–491. https://egazette.gov.in/WriteReadData/2026/276813.pdf (text consulted via IBRsource, 2026-11-23).
The citation refers to the government publication. Cite the Gazette, not this website.