2. Definitions. ─ (1) In these regulations, unless the context otherwise requires,-
(a)“Act” means the Boilers Act, 2025 (12 of 2025);
(b)“Appraisal Committee” means a Committee constituted by the Central Boilers Board to evaluate the performance of a firm or a company applying for recognition as Inspecting Authority;
(c)“Central Boilers Board Examination Standing Committee” means a Committee constituted by the Central Boilers Board to conduct examination for recognition of competent persons;
(d)“design pressure of boiler”, -
(i)in relation to a natural or assisted circulation boiler means the maximum allowable working pressure in the steam drum of the boiler;
(ii)in relation to an once through forced-circulation boiler means the maximum allowable working pressure at the final superheater steam outlet;
(e)“design temperature”,-
(i)for unheated components means the fluid temperature inside the component, under operation;
(ii)for heated components, means the fluid temperature inside the component under sustained conditions increased by specified code allowances;
(f)“Evaluation Committee” means a committee constituted by the Central Government to evaluate the performance of firm or a company applying for recognition as competent authority, well-known material testing laboratory, well-known steel maker, well-known foundry or forge, well-known tube or pipe maker and well-known remnant life assessment organisation;
(g)“firm” means a firm and includes a company;
(h)“Form” means the forms appended to these regulations;
(i)“maximum allowable working pressure” means the design pressure of any part, adjusted to take into account the pressure drop and hydraulic head;
(j)“pipe” means the cylindrical hollow parts, other than tube, drum or header with a design intent to carry a flow of steam or water or water-steam mixture during normal operation, including those that carry intermittent flow, such as drain pipes;
Explanation.─ For the purpose of this clause , the expression ‘pipe’ implies that there is no design intent to effect heat transfer through the wall of the pressure part;
(k)“tube” means a tubular pressure part that is either exposed over much of its length to hot gases for purposes of heat transfer or is directly butt welded to such a tubular pressure part including a tube stub on a drum or header.
(2)The words and expressions used herein and not defined but defined in the Act or the rules made thereunder shall have the meanings respectively assigned to them in that Act or the rules.
In short
Regulation 2 is the dictionary for the regulations. Sub-regulation (2) adds that any word not defined here takes its meaning from the Boilers Act, 2025 or the rules under it. See s.2 of the Act.
Definitions engineers trip over
- Design pressure depends on the boiler type. For natural or assisted circulation boilers it is the maximum allowable working pressure in the steam drum. For once-through forced-circulation boilers it is taken at the final superheater steam outlet.
- Design temperature for unheated parts is the fluid temperature inside the part in operation. For heated parts it is the fluid temperature under sustained conditions plus the specified code allowances.
- Maximum allowable working pressure is the design pressure of a part adjusted for pressure drop and hydraulic head. It is not automatically the same number as the boiler's design pressure.
- Pipe vs tube. A pipe carries steam or water with no design intent to transfer heat through its wall (drain pipes included). A tube is exposed over much of its length to hot gases for heat transfer, or is butt-welded directly to such a part, including tube stubs on drums or headers. Which one a part is decides which chapter applies, e.g. Chapter 6 for tubes and Chapter 7 for pipes.
- Firm includes a company. That matters for recognition provisions such as regulation 19.
Full list: Glossary.
Written by IBRsource editors · last edited 2026-11-20. Explanations simplify and are not a design method, testing procedure or authorisation. Requirements come from the complete regulations, the Gazette and approved documentation.
Comparison pending: the IBR 1950 text in force on 30 September 2026 is not yet established for this provision, so no change is claimed (how this works).
Orientation hints (unverified)
These candidates come from automated heading matching against DPIIT's scanned historical print edition of IBR 1950. That edition uses imperial units and riveted-construction provisions, so it is not the operative 2026 predecessor text. Regulation numbers alone never prove equivalence.
No candidate heading found in the historical print edition.
Images of the official Gazette pages that contain this regulation. Click to zoom. Compare word by word before relying on the extracted text.


Indian Boiler Regulations, 2026, reg. 2, Regulation 2, Gazette of India, Extraordinary, Part III—Section 4, No. 596, 1 October 2026, printed p.489–490. https://egazette.gov.in/WriteReadData/2026/276813.pdf (text consulted via IBRsource, 2026-11-23).