236. Fusible Plugs.─(1)Fusible plugs shall be of sufficient height and fitted in such a position as to give early protection to all parts of the boiler liable to damage by the direct application of furnace heat in the event of shortness of water.
Note: For example - In Lancashire boilers the fusible plugs shall be in the crowns of the furnaces from 305 mm to 457 mm in front of the brick work fire bridge.
(2)(a) On boilers having wet back reversing chamber, a minimum of two fusible plugs shall be fitted; one on the crown of the reversing chamber and the other on one of the tube plates. On boilers not having wet back reversing chamber, at least one fusible plug shall be provided on the front end tube plate.
(b)The plug shall be fitted in such a way that in the event of fusion of the plug, the pressure inside the boiler shall push the pellets out.
In short
Regulation 236 sets where fusible plugs go, so that they protect parts exposed to direct furnace heat if water runs short. Fusible plugs are among the fittings required by regulation 181.
Key points
- (1) Fusible plugs must be of sufficient height and placed to give early protection to all parts liable to damage from direct furnace heat when water is short.
- Example in a note: in Lancashire boilers, plugs go in the furnace crowns, from 305 mm to 457 mm in front of the brick work fire bridge.
- (2)(a) Boilers with a wet back reversing chamber need a minimum of two fusible plugs: one on the reversing chamber crown and one on one of the tube plates. Boilers without one need at least one plug on the front end tube plate.
- (2)(b) Plugs must be fitted so that, if the plug fuses, boiler pressure pushes the pellets out.
See regulation 237 to regulation 239 for plug type, material and attachment.
Written by IBRsource editors · last edited 2026-11-20. Explanations simplify and are not a design method, testing procedure or authorisation. Requirements come from the complete regulations, the Gazette and approved documentation.
Original drawings for this regulation
Comparison pending: the IBR 1950 text in force on 30 September 2026 is not yet established for this provision, so no change is claimed (how this works).
Orientation hints (unverified)
These candidates come from automated heading matching against DPIIT's scanned historical print edition of IBR 1950. That edition uses imperial units and riveted-construction provisions, so it is not the operative 2026 predecessor text. Regulation numbers alone never prove equivalence.
No candidate heading found in the historical print edition.
Images of the official Gazette pages that contain this regulation. Click to zoom. Compare word by word before relying on the extracted text.

Indian Boiler Regulations, 2026, reg. 236, Regulation 236, Gazette of India, Extraordinary, Part III—Section 4, No. 596, 1 October 2026, printed p.639. https://egazette.gov.in/WriteReadData/2026/276813.pdf (text consulted via IBRsource, 2026-11-23).
The citation refers to the government publication. Cite the Gazette, not this website.