Indian Boiler Regulations, 2026 · Chapter 5 · Valves, Gauges and Auxiliaries
Regulation 222. Blow-down cock or valve and pipes
Not yet checked against the official Gazette; verify before relying on it.
222. Blow-down cock or valve and pipes.─ (1) The blow-down cock or valve shall be of substantial construction.
(2)The waste pipe attached to the cock or valve shall not be bound fast in arch or brick work and shall discharge at a point where there is no danger of injury to any person.
(3)These pipes shall not be connected to a pipe common to another boiler.
(4)The continuous blow-downs may, however be connected to a common header discharging freely to an adequately vented tank or sump.
(5)The headers shall be of sufficiently large cross- section and the blow- off tank shall be provided with a vent pipe free from valves and of sufficient size to prevent accumulation of pressure. If, however, the tank is intended for collecting flash steam, a safety valve of adequate capacity shall be provided.
(6)The tank shall be so located that all parts will be accessible for inspection.
In short
Regulation 222 covers the blow-down cock or valve and its waste pipes and blow-off tank.
Key points
- (1) The blow-down cock or valve must be of substantial construction.
- (2) The waste pipe must not be bound fast in arch or brick work, and must discharge where there is no danger of injury to any person.
- (5) Headers must have a sufficiently large cross-section. The blow-off tank needs a vent pipe free from valves and big enough to prevent pressure building up.
- (6) The tank must be located so that all parts are accessible for inspection.
Watch out
- (3) Blow-down pipes must not be connected to a pipe common to another boiler.
- (4) Continuous blow-downs, however, may share a common header discharging freely to an adequately vented tank or sump.
- (5) If the tank collects flash steam, it needs a safety valve of adequate capacity.
Written by IBRsource editors · last edited 2026-11-20. Explanations simplify and are not a design method, testing procedure or authorisation. Requirements come from the complete regulations, the Gazette and approved documentation.
Original drawings for this regulation
Comparison pending: the IBR 1950 text in force on 30 September 2026 is not yet established for this provision, so no change is claimed (how this works).
Orientation hints (unverified)
These candidates come from automated heading matching against DPIIT's scanned historical print edition of IBR 1950. That edition uses imperial units and riveted-construction provisions, so it is not the operative 2026 predecessor text. Regulation numbers alone never prove equivalence.
No candidate heading found in the historical print edition.
Images of the official Gazette pages that contain this regulation. Click to zoom. Compare word by word before relying on the extracted text.

Indian Boiler Regulations, 2026, reg. 222, Regulation 222, Gazette of India, Extraordinary, Part III—Section 4, No. 596, 1 October 2026, printed p.637. https://egazette.gov.in/WriteReadData/2026/276813.pdf (text consulted via IBRsource, 2026-11-23).
The citation refers to the government publication. Cite the Gazette, not this website.