Regulation 197. Over Pressure of Safety Valves

Official text — not yet verifiedGazette 1 Oct 2026 · printed p. 631

Not yet checked against the official Gazette; verify before relying on it.

Reproduced from the Gazette of India · verification status above

197. Over Pressure of Safety Valves.─ (1) The safety valves shall be so designed that they attain rated discharge capacity with the over pressure not greater than that given in regulation 193 to 195; provided that the safety valves which have a discharge area less than 80 per cent of the flow area, the over pressure at which the design lift is attained shall not exceed 10 percent of the set pressure.

(2)For safety valves having discharge area 80 per cent of more of the flow area, the over pressure at which the design lift is attained shall not exceed 5 per cent of set pressure.

Referenced provisions

Reg. 193 · Reg. 195

Calculator (on SteamCalc, a separate free site · calculation aid, engineering review pending)

Safety valve calculator, over-pressure at which rated capacity is reached

Independent explanation — not the law · draft · engineer review in progress

In short

Regulation 197 limits the over pressure at which safety valves reach their rated discharge capacity and design lift.

Key points

  • (1) Safety valves must reach rated discharge capacity with over pressure not greater than that given in regulations 193 to 195.
  • (1) Where the discharge area is less than 80 per cent of the flow area, design lift must be reached at an over pressure not exceeding 10 percent of set pressure.
  • (2) Where the discharge area is 80 per cent or more of the flow area, design lift must be reached at an over pressure not exceeding 5 per cent of set pressure.

Written by IBRsource editors · last edited 2026-11-20. Explanations simplify and are not a design method, testing procedure or authorisation. Requirements come from the complete regulations, the Gazette and approved documentation.

Comparison pending: the IBR 1950 text in force on 30 September 2026 is not yet established for this provision, so no change is claimed (how this works).

Orientation hints (unverified)

These candidates come from automated heading matching against DPIIT's scanned historical print edition of IBR 1950. That edition uses imperial units and riveted-construction provisions, so it is not the operative 2026 predecessor text. Regulation numbers alone never prove equivalence.

No candidate heading found in the historical print edition.

Images of the official Gazette pages that contain this regulation. Click to zoom. Compare word by word before relying on the extracted text.

Instrument
Indian Boiler Regulations, 2026 (made by the Central Boilers Board under s.40 of the Boilers Act, 2025)
Notification
F.No. P-30014/3/2021-Boiler dated 7 Aug 2026
Published
Gazette of India, Extraordinary, Part III Sec. 4, No. 596, 1 Oct 2026 (CG-DL-E-06102026-276813)
In force
1 Oct 2026 (reg. 1(3): date of publication in the Official Gazette)
Printed Gazette page
631
PDF page index
631 · open official e-Gazette PDF
Extraction
pdftotext layout mode, sequential regulation detector · text hash db1448f41c6dae9a
Verification
Official text — not yet verified
Amendments checked
None known after 1 Oct 2026 as of build date (not a guarantee). Amendment log
How to cite

Indian Boiler Regulations, 2026, reg. 197, Regulation 197, Gazette of India, Extraordinary, Part III—Section 4, No. 596, 1 October 2026, printed p.631. https://egazette.gov.in/WriteReadData/2026/276813.pdf (text consulted via IBRsource, 2026-11-23).

The citation refers to the government publication. Cite the Gazette, not this website.

Help improve this page

Engineers like you keep IBRsource accurate. Every checked correction or tip helps the next reader.