Indian Boiler Regulations, 2026 · Chapter 4 · Fusion Welded Drums for Water Tube Boilers and Superheaters

Regulation 148. Constructional details and preparation for welding

Official text — not yet verifiedGazette 1 Oct 2026 · printed pp. 586–587

Not yet checked against the official Gazette; verify before relying on it.

Reproduced from the Gazette of India · verification status above

148. Constructional details and preparation for welding.─ (1) Before starting the construction work, the manufacturer shall furnish to Inspecting Authority, a fully dimensioned sectional drawing reflecting therein complete details of construction of the drum for approval.

(2)Fully dimensioned drawings of the proposed welds preparations of the main seams drawn to a scale, clearly reflecting therein all the relevant details shall be furnished.

(3)Sketches showing details of the welds preparations for the attachment of the stand pipes, branch pipes and seating and their locations relative to the longitudinal and circumferential seams and to other openings shall be furnished.

Independent explanation — not the law · draft · engineer review in progress

In short

Before construction starts, the manufacturer must submit drawings to the Inspecting Authority.

Key points

  • (1) A fully dimensioned sectional drawing with complete drum construction details, for approval.
  • (2) Fully dimensioned, scaled drawings of the weld preparations for the main seams.
  • (3) Sketches of weld preparations for stand pipes, branch pipes and seatings, and their positions relative to the longitudinal and circumferential seams and other openings.

Written by IBRsource editors · last edited 2026-11-20. Explanations simplify and are not a design method, testing procedure or authorisation. Requirements come from the complete regulations, the Gazette and approved documentation.

Comparison pending: the IBR 1950 text in force on 30 September 2026 is not yet established for this provision, so no change is claimed (how this works).

Orientation hints (unverified)

These candidates come from automated heading matching against DPIIT's scanned historical print edition of IBR 1950. That edition uses imperial units and riveted-construction provisions, so it is not the operative 2026 predecessor text. Regulation numbers alone never prove equivalence.

Historical 1950-edition reg.Heading as OCR'dHeading similaritySource image
8Welding100%Chapter I (DPIIT scan), image 3
524Preparation for inspection73%Chapter XI (DPIIT scan), image 7

Amendment history of the candidate IBR 1950 regulations: Reg. 8 (2 amendments)

IBR 1950 regulation 8 as last published in the DPIIT web edition (archived 2022)

Unofficial archived copy, not verified; see the regulation 8 page for its amendments.

Reg. 8
Welding:-

(a) The use of welding in the construction of boilers shall be permitted only where specifically provided for in the standard conditions.

IBR 1950 regulation 524 as last published in the DPIIT web edition (archived 2022)

Unofficial archived copy, not verified; see the regulation 524 page for its amendments.

Reg. 524, Reg. 525
STANDARD CONDITIONS FOR THE DESIGN AND CONSTRUCTION OF ECONOMISER, FEED PIPES, FEED HEATERS AND OTHER SIMILAR VESSELS

REGULATIONS FOR REGISTRATION AND INSPECTION OF ECONOMISERS AND FEED PIPES

Preparation for inspection

a)

At each inspection the economiser shall be emptied and thoroughly cleaned internally and externally and in the flues. All mountings shall be opened up and all caps, doors and blank flanges removed to permit adequate inspection.
b) The owner of an economiser to which this Regulation is applicable shall obtain the approval of the Chief Inspector in writing to the method of disconnection which he proposes to use and shall be responsible for ensuring that the method so approved is followed in practice.


Reg. 525

STANDARD CONDITIONS FOR THE DESIGN AND CONSTRUCTION OF ECONOMISER, FEED PIPES, FEED HEATERS AND OTHER SIMILAR VESSELS

REGULATIONS FOR REGISTRATION AND INSPECTION OF ECONOMISERS AND FEED PIPES

Procedure for Registration
a) On receipt of an application for registration the Inspector shall, after the economiser has been prepared for examination, take full particulars of the design and ascertain the working pressure allowed by the Regulations.
b)

The fitness of the economiser parts shall be determined as per the following formulae:-

(i)

Cast Iron Smooth Tube Economisers with Pressed Socket Joints.

WP = AZ + 225N Eqn.(124)
70a n

Where,

WP=Design pressure in pounds per square inch (gauge).
A= Area of contact surface of a single socket, square inches.
a= Cross sectional area measured on the mean diameter of a socket hole, in square inches.
Z=Breakdown load of an unreinforced socket joint in pounds.
N=Number of stays per header.
n=Number of sockets per header.

For existing standard designs the breakdown load of an unreinforced socket joint shall be taken as not greater than 13,500 lbs. For designs not already in use before the date of this standard the corresponding figure shall be taken as not greater than 75 per cent of the load as determined by experiment.
(ii) Headers of approximately rectangular cross section.

WP = C(t-2) Eqn.(125)
b²
Where,

t = Thickness in thirty-second of an inch.
b = Distance between the sides of header supporting the surface, in inches.
WP= Design pressure, in pounds per square inch (gauge)
C = 11 where the water side surface is flat

= 22 where the water side surface is curved, provided that the curvature is continued without interruption and the thickness at each end of the side is not less than that determined with C=11.

In no case, however, shall the thickness of the side of a header be less than 16 thirty-seconds of an inch at any part.
Next >>>

Images of the official Gazette pages that contain this regulation. Click to zoom. Compare word by word before relying on the extracted text.

Instrument
Indian Boiler Regulations, 2026 (made by the Central Boilers Board under s.40 of the Boilers Act, 2025)
Notification
F.No. P-30014/3/2021-Boiler dated 7 Aug 2026
Published
Gazette of India, Extraordinary, Part III Sec. 4, No. 596, 1 Oct 2026 (CG-DL-E-06102026-276813)
In force
1 Oct 2026 (reg. 1(3): date of publication in the Official Gazette)
Printed Gazette page
586–587
PDF page index
586–587 · open official e-Gazette PDF
Extraction
pdftotext layout mode, sequential regulation detector · text hash 1d7d5a713c5f58bf
Verification
Official text — not yet verified
Amendments checked
None known after 1 Oct 2026 as of build date (not a guarantee). Amendment log
How to cite

Indian Boiler Regulations, 2026, reg. 148, Regulation 148, Gazette of India, Extraordinary, Part III—Section 4, No. 596, 1 October 2026, printed p.586–587. https://egazette.gov.in/WriteReadData/2026/276813.pdf (text consulted via IBRsource, 2026-11-23).