Indian Boiler Regulations, 2026 · Chapter 4 · Fusion Welded Drums for Water Tube Boilers and Superheaters

Regulation 150. Cylindrical Shell of Drums

Official text — not yet verifiedGazette 1 Oct 2026 · printed p. 587

Not yet checked against the official Gazette; verify before relying on it.

Reproduced from the Gazette of India · verification status above

150. Cylindrical Shell of Drums.─

(1)Each drum shell plate shall be of cylindrical form to the extreme edges of the plate.

(2)The bending shall be done entirely by machine and local heating or hammering is prohibited.

(3)Where the plates are bent to an internal diameter less than 20 times of the plate thickness, they shall be efficiently heat-treated after bending or combined with final post weld heat treatment.

Independent explanation — not the law · draft · engineer review in progress

In short

Drum shell plates must be cylindrical right to their edges and bent entirely by machine.

Key points

  • (3) Plates bent to an internal diameter less than 20 times the plate thickness must be efficiently heat treated after bending, or this may be combined with the final post weld heat treatment.

Watch out

  • Local heating or hammering during bending is prohibited.

Written by IBRsource editors · last edited 2026-11-20. Explanations simplify and are not a design method, testing procedure or authorisation. Requirements come from the complete regulations, the Gazette and approved documentation.

Comparison pending: the IBR 1950 text in force on 30 September 2026 is not yet established for this provision, so no change is claimed (how this works).

Orientation hints (unverified)

These candidates come from automated heading matching against DPIIT's scanned historical print edition of IBR 1950. That edition uses imperial units and riveted-construction provisions, so it is not the operative 2026 predecessor text. Regulation numbers alone never prove equivalence.

No candidate heading found in the historical print edition.

Images of the official Gazette pages that contain this regulation. Click to zoom. Compare word by word before relying on the extracted text.

Instrument
Indian Boiler Regulations, 2026 (made by the Central Boilers Board under s.40 of the Boilers Act, 2025)
Notification
F.No. P-30014/3/2021-Boiler dated 7 Aug 2026
Published
Gazette of India, Extraordinary, Part III Sec. 4, No. 596, 1 Oct 2026 (CG-DL-E-06102026-276813)
In force
1 Oct 2026 (reg. 1(3): date of publication in the Official Gazette)
Printed Gazette page
587
PDF page index
587 · open official e-Gazette PDF
Extraction
pdftotext layout mode, sequential regulation detector · text hash 1f5429916d289299
Verification
Official text — not yet verified
Amendments checked
None known after 1 Oct 2026 as of build date (not a guarantee). Amendment log
How to cite

Indian Boiler Regulations, 2026, reg. 150, Regulation 150, Gazette of India, Extraordinary, Part III—Section 4, No. 596, 1 October 2026, printed p.587. https://egazette.gov.in/WriteReadData/2026/276813.pdf (text consulted via IBRsource, 2026-11-23).

The citation refers to the government publication. Cite the Gazette, not this website.

Help improve this page

Engineers like you keep IBRsource accurate. Every checked correction or tip helps the next reader.