Indian Boiler Regulations, 2026 · Chapter 4 · Fusion Welded Drums for Water Tube Boilers and Superheaters
Regulation 143. Materials of construction for fusion welded Boiler Drums
Not yet checked against the official Gazette; verify before relying on it.
143. Materials of construction for fusion welded Boiler Drums.─(1) For plates to be used in the construction of fusion welded boilers drums, requirements of Chapter-2 shall apply.
(2)Plates having thickness of more than 50 mm, before being fabricated, shall be uniformly heat treated to produce grain refinement and heat treatment involving quenching in a liquid medium is not permitted.
In short
Plates for fusion welded boiler drums must meet the requirements of Chapter 2.
Key points
- (2) Plates thicker than 50 mm must be uniformly heat treated for grain refinement before fabrication.
Watch out
- Heat treatment involving quenching in a liquid medium is not permitted for these plates.
Written by IBRsource editors · last edited 2026-11-20. Explanations simplify and are not a design method, testing procedure or authorisation. Requirements come from the complete regulations, the Gazette and approved documentation.
Comparison pending: the IBR 1950 text in force on 30 September 2026 is not yet established for this provision, so no change is claimed (how this works).
Orientation hints (unverified)
These candidates come from automated heading matching against DPIIT's scanned historical print edition of IBR 1950. That edition uses imperial units and riveted-construction provisions, so it is not the operative 2026 predecessor text. Regulation numbers alone never prove equivalence.
| Historical 1950-edition reg. | Heading as OCR'd | Heading similarity | Source image |
|---|---|---|---|
| 626 | Materials | 100% | Chapter XV (DPIIT scan), image 1 |
Amendment history of the candidate IBR 1950 regulation: Reg. 626 (1 amendment)
IBR 1950 regulation 626 as last published in the DPIIT web edition (archived 2022)
Unofficial archived copy, not verified; see the regulation 626 page for its amendments.
| Reg. 626 FEED WATER FOR BOILER | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Tests shall be carried out as prescribed in the appropriate clauses of IS : 3025-1964* and IS : 3550-1965! as indicated against the characteristics in Table 1.
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Images of the official Gazette pages that contain this regulation. Click to zoom. Compare word by word before relying on the extracted text.

Indian Boiler Regulations, 2026, reg. 143, Regulation 143, Gazette of India, Extraordinary, Part III—Section 4, No. 596, 1 October 2026, printed p.586. https://egazette.gov.in/WriteReadData/2026/276813.pdf (text consulted via IBRsource, 2026-11-23).
The citation refers to the government publication. Cite the Gazette, not this website.