Indian Boiler Regulations, 2026 · Chapter 2 · Materials of Construction
Regulation 44. Facilities for inspection
Not yet checked against the official Gazette; verify before relying on it.
44. Facilities for inspection.─ The maker shall adopt a system of making the ingots, billets, slabs, plates, bars, etc. so as to enable the finished material to be traced to the original charge, and the Inspector or Competent Person, as the case may be, shall be given every facility by maker for tracing all plates and bars to their respective charges, and for witnessing the required tests and when Inspector or Competent Person, as the case may be is satisfied with the material and with the results of the tests, the Inspector or Competent Person, as the case may be, shall be provided two copies of test reports of the material for his signature.
In short
The maker must use a system for ingots, billets, slabs, plates and bars that lets finished material be traced to its original charge.
Key points
- The maker gives the Inspector or Competent Person every facility to trace plates and bars to their charges and to witness the required tests.
- Once satisfied with the material and the test results, the Inspector or Competent Person is given two copies of the material test reports for signature.
Written by IBRsource editors · last edited 2026-11-20. Explanations simplify and are not a design method, testing procedure or authorisation. Requirements come from the complete regulations, the Gazette and approved documentation.
Comparison pending: the IBR 1950 text in force on 30 September 2026 is not yet established for this provision, so no change is claimed (how this works).
Orientation hints (unverified)
These candidates come from automated heading matching against DPIIT's scanned historical print edition of IBR 1950. That edition uses imperial units and riveted-construction provisions, so it is not the operative 2026 predecessor text. Regulation numbers alone never prove equivalence.
| Historical 1950-edition reg. | Heading as OCR'd | Heading similarity | Source image |
|---|---|---|---|
| 524 | Preparation for inspection | 72% | Chapter XI (DPIIT scan), image 7 |
IBR 1950 regulation 524 as last published in the DPIIT web edition (archived 2022)
Unofficial archived copy, not verified; see the regulation 524 page for its amendments.
| Reg. 524, Reg. 525 REGULATIONS FOR REGISTRATION AND INSPECTION OF ECONOMISERS AND FEED PIPES | |||||||||||||||||||
| |||||||||||||||||||
|
REGULATIONS FOR REGISTRATION AND INSPECTION OF ECONOMISERS AND FEED PIPES | |||||||||||||||||||
|
| Next >>> |
Images of the official Gazette pages that contain this regulation. Click to zoom. Compare word by word before relying on the extracted text.

Indian Boiler Regulations, 2026, reg. 44, Regulation 44, Gazette of India, Extraordinary, Part III—Section 4, No. 596, 1 October 2026, printed p.521. https://egazette.gov.in/WriteReadData/2026/276813.pdf (text consulted via IBRsource, 2026-11-23).
The citation refers to the government publication. Cite the Gazette, not this website.