BETAIndependent engineering reference. Source-text verification is ongoing.Verification ongoing.Verification status →
IBRsourceIndian Boiler Regulations, made clear

Indian Boiler Regulations, 2026 · Chapter 11 · Standard Conditions for the Design and Construction of Economisers, Feed Pipes, Feed Heaters and Other Similar Vessels

Regulation 376. Valves and mountings

Official text — not yet verifiedGazette 1 Oct 2026 · printed pp. 749–750

Not yet checked against the official Gazette; verify before relying on it.

Reproduced from the Gazette of India · verification status above

376. Valves and mountings.─ (1) All economisers shall be provided with thermometers for measuring water temperature adjacent to the inlet and outlet connections.

(2)(a)A valve which shall prevent increase of pressure beyond a predetermined limit shall be fitted to every economiser and the design shall provide against unauthorized interference with the loading. Economisers with pressure parts of cast iron and arranged in groups of tiers connected by circulating piping shall have a relief valve fixed on each group or tier. Relief valves shall have a minimum orifice diameter of 19 mm.

(b)The relief valve capacity shall be calculated on the basis of economiser thermal capacity.

(3)Pressure gauge for indicating the pressure in the economiser shall be constructed as per regulation 232.

(4)Air release valves shall be provided for the release of air at all points where air accumulation may occur.

(5)Blow off drain valves shall be provided for complete drainage of water in the economiser.

(6)Economiser provided with means for heating the incoming feed by mixing it with hot water from the economiser outlet, shall have a non-return valve in the hot water return line.

(7)In every case, a reserve flue shall be provided for by passing the flue gases when no water is being fed to the boiler through the economiser where it is not integral with boiler.

(8)To relieve the economisers of excessive pressure accumulation due to internal explosion doors preferably of horizontally hinged ‘self-sealing’ type shall be fitted.

(9)All valves and mountings shall satisfactorily withstand a hydraulic test to the same pressure as will be applied to the economiser during its registration.

(10)Alternative means of feeding the boiler other than through the economiser shall be provided.

(11)A non-return valve shall be provided in the hot feed line between the economiser and the boiler to prevent the discharge of steam or water from the boiler into the economiser.

Referenced provisions

Reg. 232

Independent explanation — not the law · draft · engineer review in progress

In short

Regulation 376 lists the valves, mountings and safety arrangements every economiser must have.

Key points

  • (1) Thermometers for water temperature next to the inlet and outlet connections.
  • (2)(a) A valve that stops pressure rising beyond a predetermined limit, designed against unauthorised interference with the loading. Cast iron economisers in groups or tiers linked by circulating piping need a relief valve on each group or tier. Relief valves need a minimum orifice diameter of 19 mm.
  • (2)(b) Relief valve capacity is based on the economiser's thermal capacity.
  • (3) A pressure gauge constructed as per regulation 232.
  • (4) Air release valves wherever air may collect.
  • (5) Blow off drain valves for complete drainage.
  • (6) If incoming feed is heated by mixing with hot water from the outlet, a non-return valve in the hot water return line.
  • (7) Where the economiser is not integral with the boiler, a reserve flue to bypass the flue gases when no water is fed through it.
  • (8) Explosion doors, preferably horizontally hinged self-sealing type.
  • (9) All valves and mountings must withstand the same hydraulic test pressure as the economiser at registration.
  • (10) An alternative way of feeding the boiler other than through the economiser.
  • (11) A non-return valve in the hot feed line between economiser and boiler, so steam or water cannot discharge from the boiler into the economiser.

Written by IBRsource editors · last edited 2026-11-20. Explanations simplify and are not a design method, testing procedure or authorisation. Requirements come from the complete regulations, the Gazette and approved documentation.

Comparison pending: the IBR 1950 text in force on 30 September 2026 is not yet established for this provision, so no change is claimed (how this works).

Orientation hints (unverified)

These candidates come from automated heading matching against DPIIT's scanned historical print edition of IBR 1950. That edition uses imperial units and riveted-construction provisions, so it is not the operative 2026 predecessor text. Regulation numbers alone never prove equivalence.

Historical 1950-edition reg.Heading as OCR'dHeading similaritySource image
368Other Fittings and Mountings79%Chapter VIII (DPIIT scan), image 36
IBR 1950 regulation 368 as last published in the DPIIT web edition (archived 2022)

Unofficial archived copy, not verified; see the regulation 368 page for its amendments.

Reg. 368, Reg. 369

Bronze Screwed and Socketed joints and mountings and fittings of bronze

Mountings and fittings of bronze upto 76 mm (3”) diameter may be attached directly to steel pipes by screwing when the pressures and temperatures do not exceed 8.5 kg/cm² (120 lbs./sq.in.) and 225°C (435°F) respectively; where tapered threads are employed, such joints may be used for pressures not exceeding 17.6 kg/cm² (250 lbs./sq. in.). Bronze fittings above 76 mm (3”) diameter shall be of flanged construction.



Reg. 369

Reducing Valve

Where a reducing valve is installed in a pipe line the pipe line and accessories on the low pressure side of the reducing valve shall be protected by a suitable safety valve or valves so adjusted as to permit the steam to escape as soon as the safe working pressure is exceeded or by a suitable appliance for cutting off automatically the supply of steam as soon as the safe working pressure is exceeded.

Images of the official Gazette pages that contain this regulation. Click to zoom. Compare word by word before relying on the extracted text.

Instrument
Indian Boiler Regulations, 2026 (made by the Central Boilers Board under s.40 of the Boilers Act, 2025)
Notification
F.No. P-30014/3/2021-Boiler dated 7 Aug 2026
Published
Gazette of India, Extraordinary, Part III Sec. 4, No. 596, 1 Oct 2026 (CG-DL-E-06102026-276813)
In force
1 Oct 2026 (reg. 1(3): date of publication in the Official Gazette)
Printed Gazette page
749–750
PDF page index
749–750 · open official e-Gazette PDF
Extraction
pdftotext layout mode, sequential regulation detector · text hash c4c8830fd005c97e
Verification
Official text — not yet verified
Amendments checked
None known after 1 Oct 2026 as of build date (not a guarantee). Amendment log
How to cite

Indian Boiler Regulations, 2026, reg. 376, Regulation 376, Gazette of India, Extraordinary, Part III—Section 4, No. 596, 1 October 2026, printed p.749–750. https://egazette.gov.in/WriteReadData/2026/276813.pdf (text consulted via IBRsource, 2026-11-23).

The citation refers to the government publication. Cite the Gazette, not this website.

Help improve this page

Engineers like you keep IBRsource accurate. Every checked correction or tip helps the next reader.