Regulation 372. Construction of headers

Official text — not yet verifiedGazette 1 Oct 2026 · printed p. 747

Not yet checked against the official Gazette; verify before relying on it.

Reproduced from the Gazette of India · verification status above

372.Construction of headers.─(1)The headers shall be constructed in accordance with regulation 125.

(2)Branches shall be secured by one of the following methods, namely: -

(a)Expanded, belled and welded.

(b)Strength welded with additional securing means.

(c)Full depth strength weld.

(d)Branches less than 51 mm bore may be screwed and seal welded.

(3)Open ends of forged seamless steel tube headers may be closed by forging, or the ends may be secured by bolting, screwing, or welding in an approved manner.

Referenced provisions

Reg. 125

Independent explanation — not the law · draft · engineer review in progress

In short

Regulation 372 covers the construction of economiser headers and how branches and open ends are secured.

Key points

  • (1) Headers are built in accordance with regulation 125.
  • (2) Branches are secured by one of these methods:
  • (a) expanded, belled and welded;
  • (b) strength welded with additional securing means;
  • (c) full depth strength weld;
  • (d) for branches less than 51 mm bore, screwed and seal welded.
  • (3) Open ends of forged seamless steel tube headers may be closed by forging, or secured by bolting, screwing or welding in an approved manner.

Written by IBRsource editors · last edited 2026-11-20. Explanations simplify and are not a design method, testing procedure or authorisation. Requirements come from the complete regulations, the Gazette and approved documentation.

Comparison pending: the IBR 1950 text in force on 30 September 2026 is not yet established for this provision, so no change is claimed (how this works).

Orientation hints (unverified)

These candidates come from automated heading matching against DPIIT's scanned historical print edition of IBR 1950. That edition uses imperial units and riveted-construction provisions, so it is not the operative 2026 predecessor text. Regulation numbers alone never prove equivalence.

No candidate heading found in the historical print edition.

Images of the official Gazette pages that contain this regulation. Click to zoom. Compare word by word before relying on the extracted text.

Instrument
Indian Boiler Regulations, 2026 (made by the Central Boilers Board under s.40 of the Boilers Act, 2025)
Notification
F.No. P-30014/3/2021-Boiler dated 7 Aug 2026
Published
Gazette of India, Extraordinary, Part III Sec. 4, No. 596, 1 Oct 2026 (CG-DL-E-06102026-276813)
In force
1 Oct 2026 (reg. 1(3): date of publication in the Official Gazette)
Printed Gazette page
747
PDF page index
747 · open official e-Gazette PDF
Extraction
pdftotext layout mode, sequential regulation detector · text hash 3391e3a1e7597da3
Verification
Official text — not yet verified
Amendments checked
None known after 1 Oct 2026 as of build date (not a guarantee). Amendment log
How to cite

Indian Boiler Regulations, 2026, reg. 372, Regulation 372, Gazette of India, Extraordinary, Part III—Section 4, No. 596, 1 October 2026, printed p.747. https://egazette.gov.in/WriteReadData/2026/276813.pdf (text consulted via IBRsource, 2026-11-23).

The citation refers to the government publication. Cite the Gazette, not this website.

Help improve this page

Engineers like you keep IBRsource accurate. Every checked correction or tip helps the next reader.