Indian Boiler Regulations, 2026 · Chapter 11 · Standard Conditions for the Design and Construction of Economisers, Feed Pipes, Feed Heaters and Other Similar Vessels

Regulation 369. Economiser water outlet temperature

Official text — not yet verifiedGazette 1 Oct 2026 · printed p. 747

Not yet checked against the official Gazette; verify before relying on it.

Reproduced from the Gazette of India · verification status above

369. Economiser water outlet temperature.─ The design condition shall be such that the maximum outlet water temperature of the economiser shall be at least 22°C below the saturated steam temperature in the boiler drum:

Provided that this requirement shall not apply to economizers used on low pressure water heating system working at pressure less than 36.5 m head of water.

Independent explanation — not the law · draft · engineer review in progress

In short

Regulation 369 requires the economiser to be designed so that its maximum outlet water temperature is at least 22°C below the saturated steam temperature in the boiler drum.

Watch out

  • Proviso: this does not apply to economisers on low pressure water heating systems working at less than 36.5 m head of water.

Written by IBRsource editors · last edited 2026-11-20. Explanations simplify and are not a design method, testing procedure or authorisation. Requirements come from the complete regulations, the Gazette and approved documentation.

Comparison pending: the IBR 1950 text in force on 30 September 2026 is not yet established for this provision, so no change is claimed (how this works).

Orientation hints (unverified)

These candidates come from automated heading matching against DPIIT's scanned historical print edition of IBR 1950. That edition uses imperial units and riveted-construction provisions, so it is not the operative 2026 predecessor text. Regulation numbers alone never prove equivalence.

Historical 1950-edition reg.Heading as OCR'dHeading similaritySource image
512Economiser water outlet temperature100%Chapter XI (DPIIT scan), image 4
IBR 1950 regulation 512 as last published in the DPIIT web edition (archived 2022)

Unofficial archived copy, not verified; see the regulation 512 page for its amendments.


Reg. 512
, Reg. 513, Reg. 514
STANDARD CONDITIONS FOR THE DESIGN AND CONSTRUCTION OF ECONOMIZER, FEED PIPES, FEED HEATERS AND OTHER SIMILAR VESSELS

Constructional Requirements

Economiser water outlet temperature

The design conditions shall be such that the maximum outlet water temperature of the economiser shall be at least 40°F below the saturated steam temperature in the boiler drum:

Provided that this requirement shall not apply to economisers used on low pressure water heating systems working at pressure less than 120 ft. head of water.



Reg. 513
STANDARD CONDITIONS FOR THE DESIGN AND CONSTRUCTION OF ECONOMIZER, FEED PIPES, FEED HEATERS AND OTHER SIMILAR VESSELS

STEEL ECONOMISER WITH OR WITHOUT CAST IRON SLEEVES ON THE TUBES

Tubes: Construction

a)

The tubes shall be manufactured in accordance with Regulation 151.
b) Suitable provision shall be made for supporting horizontal tubes at one or more intervals in their length to relieve bending stresses and these supports as well as the end connections must permit free expansion.


Reg. 514
STANDARD CONDITIONS FOR THE DESIGN AND CONSTRUCTION OF ECONOMIZER, FEED PIPES, FEED HEATERS AND OTHER SIMILAR VESSELS

STEEL ECONOMISER WITH OR WITHOUT CAST IRON SLEEVES ON THE TUBES

Tubes: Working Pressure
The working pressure of the tubes shall be calculated in accordance with Regulation 338(a), but the working metal temperature shall be taken as the maximum water temperature for which the part of the element is designed plus 11°C (20°F).

Images of the official Gazette pages that contain this regulation. Click to zoom. Compare word by word before relying on the extracted text.

Instrument
Indian Boiler Regulations, 2026 (made by the Central Boilers Board under s.40 of the Boilers Act, 2025)
Notification
F.No. P-30014/3/2021-Boiler dated 7 Aug 2026
Published
Gazette of India, Extraordinary, Part III Sec. 4, No. 596, 1 Oct 2026 (CG-DL-E-06102026-276813)
In force
1 Oct 2026 (reg. 1(3): date of publication in the Official Gazette)
Printed Gazette page
747
PDF page index
747 · open official e-Gazette PDF
Extraction
pdftotext layout mode, sequential regulation detector · text hash 8e3a923369290242
Verification
Official text — not yet verified
Amendments checked
None known after 1 Oct 2026 as of build date (not a guarantee). Amendment log
How to cite

Indian Boiler Regulations, 2026, reg. 369, Regulation 369, Gazette of India, Extraordinary, Part III—Section 4, No. 596, 1 October 2026, printed p.747. https://egazette.gov.in/WriteReadData/2026/276813.pdf (text consulted via IBRsource, 2026-11-23).