Indian Boiler Regulations, 2026 · Chapter 13 · Qualification Tests for Welders and Welding Operators

Regulation 512. Pipe groove welding

Official text — not yet verifiedGazette 1 Oct 2026 · printed pp. 837–841Figure referenced

Not yet checked against the official Gazette; verify before relying on it.

Reproduced from the Gazette of India · verification status above

512. Pipe groove welding.─ The welding position of pipe groove welding as mentioned in Figure 13/3 of this chapter shall be as following, namely:-

(i)Horizontal Rolled 13/PGR; Pipe with its axis horizontal and rolled during welding so that the weld metal is deposited from above with the axis of the weld horizontal.

(ii)Vertical Fixed 13/PGV; One test of groove welded joint with the axis of the pipe in a vertical position and the seam welded circumferentially in a horizontal position.

(iii)Horizontal Fixed 13/PGH; One test of groove welded joint with the axis of the pipe in a horizontal position and the seam welded without rotating the pipe.

(iv)Pipe Inclined 13/PGI; One test of groove welded joint with the axis of the pipe inclined 45 degree to the horizontal axis and the seam welded without rotating the pipe.

FIGURE13/LGF: Plate Groove Flat Position FIGURE13/LGH: Plate Groove Horizontal Position

FIGURE13/LGV: Plate Groove Vertical Position FIGURE13/LGO: Plate Groove Overhead Position Size: 16 x 150 x 400 mm -- 2 Nos.
TEST POSITIONS

FIGURE :13/1 PLATE GROOVE JOINTS

FIGURE13/LFF: Plate Fillet Flat Position FIGURE13/LFH: Plate Fillet Horizontal Position

FIGURE13/LFV: Plate Fillet Vertical
Position

FIGURE13/LFO: Plate Fillet Overhead Position

Size: 16 x 75 x 300 mm -- 2 Nos
TEST POSITIONS

FIGURE13/2: PLATE FILLET JOINTS (TEE)

FIGURE13/PGR: PIPE Axis Horizontal FIGURE13/PGV: Pipe Axis Vertical Welding from Top Flat Position (Pipe Rotated) Weld Horizontal position (Pipe Fixed)

FIGURE13/PGH: PIPE Axis Horizontal FIGURE13/PGI: Pipe Axis Inclined at 45o

Weld All around (Pipe Fixed) Weld All around (Pipe Fixed)

Size: Pipe Dia 127.5mm x 12.5mm thick or more

Tube Dia 76.1mm X 8.8mm thick or less

TEST POSITIONS

FIGURE13/3 PIPE/TUBE GROOVE JOINTS

Independent explanation — not the law · draft · engineer review in progress

In short

Regulation 512 defines the four test positions for pipe groove welds shown in Figure 13/3.

Key points

  • (i) Horizontal rolled, 13/PGR: pipe axis horizontal and rolled during welding, so weld metal goes on from above.
  • (ii) Vertical fixed, 13/PGV: pipe axis vertical, seam welded around in a horizontal position.
  • (iii) Horizontal fixed, 13/PGH: pipe axis horizontal, seam welded without rotating the pipe.
  • (iv) Inclined, 13/PGI: pipe axis inclined at 45 degree to the horizontal, seam welded without rotating the pipe.
  • The figure captions also show test piece sizes: plate groove 16 x 150 x 400 mm (2 Nos.), plate fillet 16 x 75 x 300 mm (2 Nos.), pipe 127.5 mm x 12.5 mm thick or more, and tube 76.1 mm x 8.8 mm thick or less.

Watch out

Written by IBRsource editors · last edited 2026-11-20. Explanations simplify and are not a design method, testing procedure or authorisation. Requirements come from the complete regulations, the Gazette and approved documentation.

Original drawings for this regulation

Comparison pending: the IBR 1950 text in force on 30 September 2026 is not yet established for this provision, so no change is claimed (how this works).

Orientation hints (unverified)

These candidates come from automated heading matching against DPIIT's scanned historical print edition of IBR 1950. That edition uses imperial units and riveted-construction provisions, so it is not the operative 2026 predecessor text. Regulation numbers alone never prove equivalence.

Historical 1950-edition reg.Heading as OCR'dHeading similaritySource image
8Welding100%Chapter I (DPIIT scan), image 3

Amendment history of the candidate IBR 1950 regulation: Reg. 8 (2 amendments)

IBR 1950 regulation 8 as last published in the DPIIT web edition (archived 2022)

Unofficial archived copy, not verified; see the regulation 8 page for its amendments.

Reg. 8
Welding:-

(a) The use of welding in the construction of boilers shall be permitted only where specifically provided for in the standard conditions.

Images of the official Gazette pages that contain this regulation. Click to zoom. Compare word by word before relying on the extracted text.

Instrument
Indian Boiler Regulations, 2026 (made by the Central Boilers Board under s.40 of the Boilers Act, 2025)
Notification
F.No. P-30014/3/2021-Boiler dated 7 Aug 2026
Published
Gazette of India, Extraordinary, Part III Sec. 4, No. 596, 1 Oct 2026 (CG-DL-E-06102026-276813)
In force
1 Oct 2026 (reg. 1(3): date of publication in the Official Gazette)
Printed Gazette page
837–841
PDF page index
837–841 · open official e-Gazette PDF
Extraction
pdftotext layout mode, sequential regulation detector · text hash e93eda4af04b31c5
Verification
Official text — not yet verified
Amendments checked
None known after 1 Oct 2026 as of build date (not a guarantee). Amendment log
How to cite

Indian Boiler Regulations, 2026, reg. 512, Regulation 512, Gazette of India, Extraordinary, Part III—Section 4, No. 596, 1 October 2026, printed p.837–841. https://egazette.gov.in/WriteReadData/2026/276813.pdf (text consulted via IBRsource, 2026-11-23).

The citation refers to the government publication. Cite the Gazette, not this website.

Help improve this page

Engineers like you keep IBRsource accurate. Every checked correction or tip helps the next reader.