Indian Boiler Regulations, 2026 · Chapter 13 · Qualification Tests for Welders and Welding Operators

Regulation 539. Additional test before rejection

Official text — not yet verifiedGazette 1 Oct 2026 · printed p. 853

Not yet checked against the official Gazette; verify before relying on it.

Reproduced from the Gazette of India · verification status above

539.Additional test before rejection .─ (1) (a) in case any of the test pieces tested in accordance with the regulations 535 to 538fail to meet the specified requirements, one further weld may be cut from the specimen and subjected to the same test.

(b)If any test piece does not reach the required standard, one further weld shall be made after sufficient retraining, and the procedure in the above regulations shall be repeated.

(c)If the repeat weld does not reach the required standard, the welder shall be deemed not to have qualified for a certificate.

(2)The decision of the competent authority on refusal to grant welder certificate shall be final.

Referenced provisions

Reg. 535 · Reg. 538

Independent explanation — not the law · draft · engineer review in progress

In short

Regulation 539 gives the retest route for test pieces tested under regulation 535 to regulation 538, before a welder is rejected.

Key points

  • (1)(a) If a test piece fails, one further piece may be cut from the specimen and given the same test.
  • (1)(b) If a test piece still fails, one further weld is made after sufficient retraining, and the test procedure is repeated.
  • (1)(c) If that repeat weld fails, the welder is deemed not qualified for a certificate.
  • (2) The Competent Authority's decision to refuse a welder certificate is final.

Watch out

  • This route allows one further weld after retraining. Regulation 533 allows two further welds.

Written by IBRsource editors · last edited 2026-11-20. Explanations simplify and are not a design method, testing procedure or authorisation. Requirements come from the complete regulations, the Gazette and approved documentation.

Comparison pending: the IBR 1950 text in force on 30 September 2026 is not yet established for this provision, so no change is claimed (how this works).

Orientation hints (unverified)

These candidates come from automated heading matching against DPIIT's scanned historical print edition of IBR 1950. That edition uses imperial units and riveted-construction provisions, so it is not the operative 2026 predecessor text. Regulation numbers alone never prove equivalence.

Historical 1950-edition reg.Heading as OCR'dHeading similaritySource image
55Additional tests before rejection98%Chapter II (DPIIT scan), image 10
66Additional Tests77%Chapter II (DPIIT scan), image 13

Amendment history of the candidate IBR 1950 regulations: Reg. 55 (1 amendment)

IBR 1950 regulation 55 as last published in the DPIIT web edition (archived 2022)

Unofficial archived copy, not verified; see the regulation 55 page for its amendments.

Reg. 55
MATERIALS OF CONSTRUCTION

SEAMLESS FERRITIC PIPES FOR HIGH TEMPERATURE SERVICE

Additional tests before rejection

(i)If any one or more tests specified in these regulations fail, two further tests of the same kind may be made on two other pipes of the same batch.  If any of these tests fails, the batch of the pipes represented may be given a further heat treatment and entire set of tests shall be repeated. 

(ii)  If the repeat tests are satisfactory, the pipes shall be accepted. If any failure in the tests should occur the entire batch of the pipes shall be rejected.

Images of the official Gazette pages that contain this regulation. Click to zoom. Compare word by word before relying on the extracted text.

Instrument
Indian Boiler Regulations, 2026 (made by the Central Boilers Board under s.40 of the Boilers Act, 2025)
Notification
F.No. P-30014/3/2021-Boiler dated 7 Aug 2026
Published
Gazette of India, Extraordinary, Part III Sec. 4, No. 596, 1 Oct 2026 (CG-DL-E-06102026-276813)
In force
1 Oct 2026 (reg. 1(3): date of publication in the Official Gazette)
Printed Gazette page
853
PDF page index
853 · open official e-Gazette PDF
Extraction
pdftotext layout mode, sequential regulation detector · text hash e8e123d77f77fc23
Verification
Official text — not yet verified
Amendments checked
None known after 1 Oct 2026 as of build date (not a guarantee). Amendment log
How to cite

Indian Boiler Regulations, 2026, reg. 539, Regulation 539, Gazette of India, Extraordinary, Part III—Section 4, No. 596, 1 October 2026, printed p.853. https://egazette.gov.in/WriteReadData/2026/276813.pdf (text consulted via IBRsource, 2026-11-23).

The citation refers to the government publication. Cite the Gazette, not this website.

Help improve this page

Engineers like you keep IBRsource accurate. Every checked correction or tip helps the next reader.