Indian Boiler Regulations, 2026 · Chapter 16 · Heat Exchangers and Pressure Vessels

Regulation 579. Initial qualification of tube to tube sheet joints

Official text — not yet verifiedGazette 1 Oct 2026 · printed pp. 863–864Formula / symbols

Not yet checked against the official Gazette; verify before relying on it.

Reproduced from the Gazette of India · verification status above

579.Initial qualification of tube to tube sheet joints.─(1)The method of joining tubes to tube sheet shall be any one of the following, namely:-

(i)Strength expansion only (without welding);

(ii)Strength welding & light expansion, or

(iii)Strength expansion & seal welding.

(2)All the above three process shall be carried out with procedure qualified by the manufacturer.

(3)(a) The boiler or boiler component manufacturer shall prepare written procedures for joints that are expanded (whether welded and expanded or expanded only) for joint strength.

(b)The boiler or boiler component manufacturer shall establish the variables that affect joint repeatability in these procedures.

(c)The procedures shall provide detailed descriptions or sketches of enhancements, such as grooves, serrations, threads, and coarse machining profiles.

(4)(a) For strength welded joints, minimum eight mock up welds are required to qualify each procedure.

(b)The mock up assembly shall essentially duplicate the tube hole configuration and tube-to-tubesheet joint design.

(5)The materials group (M No. wise), tube hole size, tube size and tube fit up with tube sheet shall simulate production.

(6)Test block arrangement shall be as given under,─

Minimum number of holes = 3-2-3 for triangular pitch.
= 3-3-3 for Square pitch

Thickness = Tube sheet thickness or 50 mm whichever is less.

(7)(a) The test block simulating the tube-sheet may be circular, square or rectangular in shape, essentially in general conformity with the tube pitch geometry.

(b)The test assembly shall consist of an array of tubes such that the tube to be tested is in the geometric center of the array and surrounded by at least one row of adjacent tubes.

(c)The test block shall extend a distance of at least one tube-sheet ligament beyond the edge of the peripheral tubes in the assembly.

(8)All tubes in the test block array shall be from the same grade of material and shall be installed using identical procedures.

(9)(a) The length of the tube used for testing the tube joint need only be sufficient to suit the test apparatus.

(b)The length of the tubes adjacent to the tube joint to be tested shall not be less than the thickness of the test block to be qualified.

Tables and formulae are shown in their extracted layout. Alignment, superscripts and subscripts may be lost. The Gazette page image is authoritative.

Independent explanation — not the law · draft · engineer review in progress

In short

This regulation sets how tube-to-tube-sheet joints are qualified before production: the joining methods allowed, the written procedures needed, and how the mock-up test block is built. Testing of the block follows regulation 580.

Key points

  • (1) Allowed joining methods: (i) strength expansion only (no welding); (ii) strength welding and light expansion; or (iii) strength expansion and seal welding.
  • (2) All three must be carried out with a procedure qualified by the manufacturer.
  • (3) For expanded joints (welded and expanded, or expanded only), the boiler or boiler component manufacturer must:
  • (a) prepare written procedures for joint strength;
  • (b) establish the variables that affect joint repeatability;
  • (c) describe or sketch enhancements such as grooves, serrations, threads and coarse machining profiles.
  • (4) Strength welded joints need at least eight mock-up welds to qualify each procedure. The mock-up must essentially duplicate the tube hole configuration and joint design.
  • (5) Material group (M No.), tube hole size, tube size and tube fit-up must simulate production.
  • (6) Test block: minimum holes 3-2-3 for triangular pitch or 3-3-3 for square pitch. Thickness is the tube sheet thickness or 50 mm, whichever is less.
  • (7) The block may be circular, square or rectangular, in general conformity with the tube pitch geometry. The tube under test sits at the geometric centre, surrounded by at least one row of adjacent tubes. The block extends at least one tube-sheet ligament beyond the peripheral tubes.
  • (8) All tubes in the array are of the same grade and installed by identical procedures.
  • (9) The tested tube only needs to be long enough for the test apparatus. Adjacent tubes must be at least as long as the thickness of the test block.

Written by IBRsource editors · last edited 2026-11-20. Explanations simplify and are not a design method, testing procedure or authorisation. Requirements come from the complete regulations, the Gazette and approved documentation.

Comparison pending: the IBR 1950 text in force on 30 September 2026 is not yet established for this provision, so no change is claimed (how this works).

Orientation hints (unverified)

These candidates come from automated heading matching against DPIIT's scanned historical print edition of IBR 1950. That edition uses imperial units and riveted-construction provisions, so it is not the operative 2026 predecessor text. Regulation numbers alone never prove equivalence.

No candidate heading found in the historical print edition.

Images of the official Gazette pages that contain this regulation. Click to zoom. Compare word by word before relying on the extracted text.

Instrument
Indian Boiler Regulations, 2026 (made by the Central Boilers Board under s.40 of the Boilers Act, 2025)
Notification
F.No. P-30014/3/2021-Boiler dated 7 Aug 2026
Published
Gazette of India, Extraordinary, Part III Sec. 4, No. 596, 1 Oct 2026 (CG-DL-E-06102026-276813)
In force
1 Oct 2026 (reg. 1(3): date of publication in the Official Gazette)
Printed Gazette page
863–864
PDF page index
863–864 · open official e-Gazette PDF
Extraction
pdftotext layout mode, sequential regulation detector · text hash cc98f7980a884d61
Verification
Official text — not yet verified
Amendments checked
None known after 1 Oct 2026 as of build date (not a guarantee). Amendment log
How to cite

Indian Boiler Regulations, 2026, reg. 579, Regulation 579, Gazette of India, Extraordinary, Part III—Section 4, No. 596, 1 October 2026, printed p.863–864. https://egazette.gov.in/WriteReadData/2026/276813.pdf (text consulted via IBRsource, 2026-11-23).

The citation refers to the government publication. Cite the Gazette, not this website.