The Boilers Act, 2025 · Chapter III
Section 7. Conditions precedent for manufacture of boiler and boiler components
Not yet checked against the official India Code text; verify before relying on it.
7. Conditions precedent for manufacture of boiler and boiler components.—No person shall manufacture or cause to be manufactured any boiler or boiler components, or both, unless—
(a)the premises or precincts wherein boiler or boiler components, or both, are manufactured, have such facilities for design and construction as may be specified by regulations;
(b)a certificate for the design and drawings of the boiler and boiler components have been granted by the inspecting authority under clause (a) of sub-section (3) of section 8;
(c)the material, mounting and fitting used in the construction of boiler or boiler components, or both, conform to such specifications as may be specified by regulations; and
(d)the person engaged in welding boiler or boiler components hold welders certificate granted by the competent authority under sub-section (4) of section 6.
Numbers in the form 21[ are India Code footnote markers that record amendments. Source: India Code, Act 12 of 2025, PDF p.9.
Commentary
Section 7 lists the conditions that must all be met before anyone manufactures, or causes to be manufactured, a boiler or boiler components. The four conditions are joined by "and", so each applies.
- (a) Facilities: the premises must have the design and construction facilities specified by regulations (section 40(2)(g)).
- (b) Design certificate: the inspecting authority must have granted a certificate for the design and drawings under section 8(3)(a).
- (c) Materials: material, mountings and fittings must conform to the specifications in the regulations (section 40(2)(h)).
- (d) Welders: persons welding the boiler or components must hold a welders certificate under section 6(4).
The section is framed as a prohibition ("No person shall"), and it reaches a person who causes manufacture as well as the manufacturer. The inspection that follows during manufacture is in section 8.
Predecessor in the Boilers Act, 1923: s.4C. Conditions before manufacturing boilers or components follow old s.4C.
- Clause (b) now requires 'a certificate for the design and drawings' granted under s.8(3)(a); the old text required design and drawings 'approved' by the Inspecting Authority.
- Clause (a) states the premises must 'have' the facilities; the old text said 'he has provided' them.
- Welders certificate must be one granted under s.6(4).
Compare the two official texts before relying on this summary.
Candidate 1923 match found automatically (96% similar), not yet confirmed by a reviewer.
| 1923 candidate | Heading | Heading sim. | Text sim. |
|---|---|---|---|
| s.4C | Conditions precedent for manufacture of boiler and boiler component | 99% | 94% |
| s.4F | Conditions precedent for repairing boiler and boiler component | 83% | 77% |
| s.4D | Inspection during manufacture | 55% | 67% |
Word-level comparison with 1923 s.4C (candidate)
struck = only in 1923 text · highlighted = only in 2025 text. India Code footnote markers are removed before comparing.