Indian Boiler Regulations, 2026 · Chapter 17 · Small Solar Boilers

Regulation 595. Valves, gauges, fittings and feed supply

Official text — not yet verifiedGazette 1 Oct 2026 · printed p. 866

Not yet checked against the official Gazette; verify before relying on it.

Reproduced from the Gazette of India · verification status above

595. Valves, gauges, fittings and feed supply.─ (1) Small solar boiler shall be fitted with the following, namely:–

(i)wash plugs for cleaning;

(ii)suitable provision to indicate the water level;

(iii)one water feeding device;

(iv)one feed pipe shall be provided with a check valve and a stop valve of a size not less than that of the pipe;

(v)suitable provision to drain the boiler water;

(vi)one steam pressure gauge having minimum 100 mm dial size; and

(vii)one safety valve for relieving the steam pressure.

(2)Safety valves shall be certified under Indian Boiler Regulations and all other fittings may be certifie d by the manufacturers of such fittings.

Independent explanation — not the law · draft · engineer review in progress

In short

This regulation lists the minimum valves, gauges and fittings for a small solar boiler and who certifies them.

Key points

  • (1) Every small solar boiler must have:
  • (i) wash plugs for cleaning;
  • (ii) suitable provision to indicate the water level;
  • (iii) one water feeding device;
  • (iv) one feed pipe with a check valve and a stop valve, each no smaller than the pipe;
  • (v) suitable provision to drain the boiler water;
  • (vi) one steam pressure gauge with a dial of at least 100 mm;
  • (vii) one safety valve for relieving the steam pressure.
  • (2) Safety valves must be certified under the Indian Boiler Regulations. All other fittings may be certified by their own manufacturers.

Written by IBRsource editors · last edited 2026-11-20. Explanations simplify and are not a design method, testing procedure or authorisation. Requirements come from the complete regulations, the Gazette and approved documentation.

Comparison pending: the IBR 1950 text in force on 30 September 2026 is not yet established for this provision, so no change is claimed (how this works).

Orientation hints (unverified)

These candidates come from automated heading matching against DPIIT's scanned historical print edition of IBR 1950. That edition uses imperial units and riveted-construction provisions, so it is not the operative 2026 predecessor text. Regulation numbers alone never prove equivalence.

Historical 1950-edition reg.Heading as OCR'dHeading similaritySource image
621Valves, Gauges, Fittings and Feed Supply100%Chapter XIV (DPIIT scan), image 2

Amendment history of the candidate IBR 1950 regulation: Reg. 621 (3 amendments)

IBR 1950 regulation 621 as last published in the DPIIT web edition (archived 2022)

Unofficial archived copy, not verified; see the regulation 621 page for its amendments.

Reg. 621, Reg. 622

Small Industrial Boilers General

Reg 621

Valves, Gauges, Fittings and Feed Supply

(a)
           Washout Plugs, etc. for cleaning:-

(i) Every boiler shall be fitted with at least 3 brass wash plugs of not less than 25 mm. diameter which shall be screwed into the openings in the shells near the bottom. In the boilers of closed system type heated by removable internal electric heating elements, the opening for these elements when suitable for cleaning purposes may be substituted for wash out openings.
(ii) Boilers not exceeding 300 mm. internal diameter may have two 25 mm. openings for cleaning one of which may be used for the attachments of the blow off valve. The openings shall be opposite to each other, wherever possible. All threaded openings in the boiler shall be provided with riveted or welded reinforcement, if necessary, to give four full threads therein.
(iii) Electric boilers of a design employing removable top cover flange for inspection and cleaning need not be fitted with washout openings and washout plug. Level gauges are not required for once through boilers.
(b) Every boiler shall be provided with at least one feed pump or other feeding device except where it is connected with a water main carrying pressure to feed the boiler or where the steam generator is operated with no extraction of steam (closed system). In the latter case, in lieu of the feeding device, a suitable connection or opening shall be provided to feed the boilers. Such connection shall be not less than 13 mm. in diameter.
(c) Subject to the provisions of this sub-regulation every boiler shall be fitted with necessary mountings and fittings as provided in Chapter VI of these regulations, and they shall be of substantial construction suitable for 7 kg/cm2. All these fittings except safety valves shall be certified by manufacturers of the fittings themselves.
(i) Feed pipe: The feed pipe shall be provided with a check valve and a stop valve of a size not less than that of the pipe. The feed water may be delivered to the boiler through the openings of the same size in the shell as that of the blow off connection.
(ii) Blow Off: Each boiler shall be equipped with a blow off connection, not less than 18 mm. in size located to drain the boiler water from the lowest water space practicable when the boiler is under pressure. Feed water shall not be introduced through the openings or connection needed for the water column, the water gauge glass or the gauge cock.
(iii) Water Gauges: Every boiler other than a coil type or a once through boiler shall be fitted with two gauge glasses not less than 150 mm. long for determining the water level. The boiler shall have the lowest visible part of the water gauge located at least 25 mm. above the lowest permissible water level.


The lowest permissible water level of vertical boilers shall be at a point one-third of the height of the shell above the bottom head or tube sheet. Where the boiler is equipped with internal furnace, the water level shall not be less than one-third of the length of the tubes above top of the furnace tube sheet.
(iv) Pressure Gauge: The steam pressure gauge shall have its dial graduated to not less than twice the maximum allowable working pressure of the boiler. The diameter of the dial shall be at least 100 mm. and the pipe connecting the pressure gauge shall be minimum 10 mm. and the connection shall be through siphon.
(v) Safety Valve: Each boiler shall be equipped with two safety valves for relieving the steam pressure. The diameter of the valve shall not be less than 19 mm.
     The minimum relieving capacity of the safety valve shall be sufficient to discharge all the steam that can be generated by the boiler without allowing the pressure to rise more than 10% above maximum allowable working pressure. The safety valve shall be connected to the boiler independently of any other steam connections, without any unnecessary intervening pipe or fitting. Such intervening pipe or fitting if unavoidable shall be not longer than the corresponding face to face dimension of a tee fitting of the same diameter and the minimum opening there through shall be at least equal to the valve inlet.

No valve of any description shall be placed between safety valve and the boiler not on the discharge pipe from the safety valve to the atmosphere.

The electrically heated boilers shall be effectively earthed with a lead of substantial cross section.


Reg. 622

Registration, Operation and Maintenance

(a) (i) The fee required to accompany an application under sub-section (1) of section 7 of the Act shall be five hundred rupees per boiler.
(ii) The annual inspection fee shall be five hundred rupees per boiler.
(b) The certificate of manufacture and test for small industrial boilers shall be furnished in Form XVII appended to these regulations.
(c) The operator for these boilers shall be a pass in Class X or equivalent.

Images of the official Gazette pages that contain this regulation. Click to zoom. Compare word by word before relying on the extracted text.

Instrument
Indian Boiler Regulations, 2026 (made by the Central Boilers Board under s.40 of the Boilers Act, 2025)
Notification
F.No. P-30014/3/2021-Boiler dated 7 Aug 2026
Published
Gazette of India, Extraordinary, Part III Sec. 4, No. 596, 1 Oct 2026 (CG-DL-E-06102026-276813)
In force
1 Oct 2026 (reg. 1(3): date of publication in the Official Gazette)
Printed Gazette page
866
PDF page index
866 · open official e-Gazette PDF
Extraction
pdftotext layout mode, sequential regulation detector · text hash 5c1caf25c7c04081
Verification
Official text — not yet verified
Amendments checked
None known after 1 Oct 2026 as of build date (not a guarantee). Amendment log
How to cite

Indian Boiler Regulations, 2026, reg. 595, Regulation 595, Gazette of India, Extraordinary, Part III—Section 4, No. 596, 1 October 2026, printed p.866. https://egazette.gov.in/WriteReadData/2026/276813.pdf (text consulted via IBRsource, 2026-11-23).

The citation refers to the government publication. Cite the Gazette, not this website.