APPENDIX-I
[See regulation 295(8)]

A. Waste Heat Boilers (Fired) upto twenty years of age used exclusively in continuous process plant. ─

(1)For Waste Heat Boilers (Fired) up to twenty years of age used exclusively in continuous process plant, at the expiry of twelve months and at twenty four months from the date of inspection carried out in accordance with the procedure provided in regulation 311 and certification of fitness issued by the concerned Competent Person in the State, and having satisfied with the operation records as given below received alongwith application in Form-IX duly filled in shall be allowed for running for another period of twelve months:—

(a)Operation data for superheater and reheater temperature excursions from the output of Data Acquisition System (DAS) or operation data for superheater temperature excursions maintained in the log sheet temperature record;

(b)History of shut downs during the previous year with their causes and actions taken;

(c)Records of any Non-Destructive test carried out on the boiler pressure parts during the year;

(d)Water quality to the boiler is maintained as per the requirement of such boilers and on line data of the quality be provided through Data Acquisition System (DAS) or through water quality record logbook maintained at plant or at source of water;

(e)Boiler tube failure record (location, number of tubes repaired/replaced).

(2)Inspection shall be carried out by the concerned Competent Person at the expiry of thirty six months as provided in regulation 311. However, in case of shutdown of fifteen days or more any time before expiry of the certification period and after six months of the certification, Competent Person shall be duly informed so that inspection can be scheduled during the said shutdown period.

B. Waste Heat Boilers (Unfired) up to twenty years of age used exclusively in continuous process plant. ─

(1)For Waste Heat Boilers (Unfired) up to twenty years of age used exclusively in continuous process plant, at the expiry of twenty-four months from the date of inspection carried out in accordance with the procedure provided in regulation 311and certification of fitness by the concerned Competent Person in the State, and having satisfied with the operation records at paragraph “A”, shall be allowed for running for another period of twenty-four months.

(2)Inspection shall be carried out by the concerned Competent Person at the expiry of forty-eight months as provided in regulation 311. However, in case of shutdown of fifteen days or more any time before expiry of the certification period and after six months of the certification, Competent Person shall be duly informed so that inspection can be scheduled during the said shutdown period.

C. Waste Heat Boilers (Fired) more than twenty years of age used exclusively in continuous process plant. ─ Boiler more than twenty years of age shall continue to be subjected to inspection as provided in regulation 311 every year to the satisfaction of concerned Competent Person in the State. However, if Remnant Life Assessment (RLA) as per the provisions of these regulations is carried out on the boiler and if found satisfactory, then procedure as given at paragraph 'A' above shall be followed.

D. Waste Heat Boilers (Unfired) more than twenty years of age used exclusively in continuous process plant. ─ Boiler more than twenty years of age shall continue to be subjected to inspection as provided in regulation 311 every year to the satisfaction of concerned Competent Person in State. However, if Remnant Life Assessment (RLA) as per the provisions of these regulations is carried out on the boiler and if found satisfactory, then procedure as given at paragraph 'B' above would be applicable.

Gazette pages