Indian Boiler Regulations, 1950 (superseded 1 Oct 2026)
Regulation 598 — Uptakes of Vertical Boilers
Text in the DPIIT web edition
Archived copy captured 03 Aug 2022 (Wayback Machine); the same page also prints regulations 599, 600, 601. The text matches the 2019 capture; amendments from 2020 onwards are probably not included. Units as printed.
| Reg. 598, Reg. 599, Reg. 600, Reg. 601 | ||||||||||||||||||||||||||||||||||||||||||||||
Reg. 599 Cross Tubes
Reg. 600 Pads Welded to shell or the attachment of Flanged Mountings
Reg. 601
| ||||||||||||||||||||||||||||||||||||||||||||||
Earlier text: the 2008 DIPP web edition
Uptakes of Vertical Boilers
The working pressure for uptake tubes of vertical boilers shall be determined by the following formula:-
(i)When an internal liner is not fitted:-
100 (t-2)
W.P. = Equation XII/33.
D
(ii)When an internal liner is fitted extending below the low water level:-
725 (t-1)²
W.P. = x Equation XII/34.
D (L+24)
Where,
W.P. is working pressure in pounds per square inch. t is thickness of the uptake in thirty seconds of an inch.
D is external diameter in inches.
L is length of the uptake in inches, measured between the circumferential seams.
In no case shall the thickness of an uptake tube be less than 3/8 inch.