Indian Boiler Regulations, 2026
Appendix K — Time limits for the various activities
Official text — not yet verifiedGazette p.995–997
Not yet checked against the official Gazette; verify before relying on it.
Open the official Gazette at this appendix
Official text · verification status above
APPENDIX- K Time limits for the various activities
| Sl. No. | Activity | Regulation/ Provision in IBR | Time limit | Authority /Person |
|---|---|---|---|---|
| (1) | (2) | (3) | (4) | (5) |
| 1. | Issue of Certificate for manufacture and test in Form- I(Part-B) and Form- I(Part-C) | 8(a) | (i) 3 days for boiler components. (ii) 7 days for boiler | Inspecting Authority |
| 2. | Issue of Inspecting Authority Certificate during erection in “Form-I(Part-E) ” | 8(a)(v) | 2 days | Inspecting Authority |
| 3. | Steam Tests of boiler | 299(1) | 30 days | Inspector |
| 4. | Issue of provisional order in Form- X after registration inspection | 300(2) | 48 Hours | Inspector |
| 5. | Assigning of Registration No. for boilers | 300 | 30 days | Chief Inspector of Boilers |
| 6. | Transfer of Memorandum of Inspection Book & Registration Book | 309 | 15 days | Chief Inspector of Boilers |
| 7. | Issue of Certificate for use of boiler in Form-XII | 310 | 48 Hours | Competent Person |
| 8. | Submission of Remnant Life Assessment report/ recommendations | 313 to 315 | 30 days from date of completion of inspection/tests | Well Known Remnant Life Assessment Organisation |
| 9. | Recognition of repairers boilers & steam pipes | 316(5) | 30 days | Chief Inspector of Boilers |
| 10. | Permission to carry out repairs/alterations in boilers | 316(3)(e)(ii) | 2 days | Chief Inspector of Boilers |
| 11 | Approval of design and manufacturing drawings for boilers and boiler components made in India | 321(1) | (i) 5 days for boilers components & boilers upto 20 TPH capacity. (ii) 15 days for boilers above 20 TPH &upto 100 TPH capacity (iii) 21 days for boilers above 100 TPH capacity | Inspecting Authority |
| 12. | Approval of materials for boilers and boiler components made outside India | 321(3) | (i) 5 days, in case of same materials as previously approved for the same design pressure & temperature (ii) 10 days, in other cases | Technical Adviser(Boilers) |
| 13. | Approval of design and manufacturing drawings for boilers and boiler components made outside India | 321(3) | 21 days | Chief Inspector of Boilers |
| 14, | Issue of Welder qualification certificate in Form-II after submission of satisfactory reports | 541 | 5 days | Competent Authority |
| 15. | Inspection during construction/ manufacture | Appendix-A | 2 days | Inspecting Authority/ Competent Person |
Table structure read from the Gazette PDF, pages 995, 996. Verification status as for the text above.
Show original extracted text (diagnostic, not authoritative)
Sl. Activity Regulation/ Time limit Authority /Person
Provision in (5)
No. (4)
IBR (i) 3 days for boiler Inspecting Authority
(1) (2) (3)
8(a) components. Inspecting Authority
1. Issue of Certificate for (ii) 7 days for boiler Inspector
Inspector
manufacture and test in Form-
I(Part-B) and Form- I(Part-C)
2. Issue of Inspecting Authority 8(a)(v) 2 days
Certificate during erection in 299(1) 30 days
“Form-I(Part-E) ”
3. Steam Tests of boiler
4. Issue of provisional order in Form- 300(2) 48 Hours
X after registration inspection
5. Assigning of Registration No. for 300 30 days Chief Inspector of
Boilers
boilers
6. Transfer of Memorandum of 309 15 days Chief Inspector of
48 Hours Boilers
Inspection Book & Registration
Competent Person
Book
7. Issue of Certificate for use of boiler 310
in Form-XII
8. Submission of Remnant Life 313 to 315 30 days from date of Well Known
316(5) Remnant Life
Assessment report/ completion of Assessment
Organisation
recommendations inspection/tests Chief Inspector of
9. Recognition of repairers boilers & 30 days Boilers
steam pipes
10. Permission to carry out 316(3)(e)(ii) 2 days Chief Inspector of
repairs/alterations in boilers Boilers
11 Approval of design and 321(1) (i) 5 days for boilers Inspecting Authority
manufacturing drawings for components & boilers
boilers and boiler components upto 20 TPH
made in India capacity.
(ii) 15 days for boilers
above 20 TPH &upto
100 TPH capacity
(iii) 21 days for boilers
above 100 TPH
capacity
12. Approval of materials for boilers 321(3) (i) 5 days, in case of same Technical
and boiler components made 321(3) materials as previously Adviser(Boilers)
outside India approved for the same
design pressure & Chief Inspector of
13. Approval of design and temperature Boilers
(ii) 10 days, in other cases21 days manufacturing drawings for boilers and boiler components made outside India
Original extracted text of the table above, continued (diagnostic)
14, Issue of Welder qualification 541 5 days Competent Authority
certificate in Form-II after submission of satisfactory reports
Original extracted text of the table above, continued (diagnostic)
15. Inspection during construction/ Appendix-A 2 days Inspecting Authority/ Competent Person
manufacture
Note: (1) Above time limits shall be applicable from the date of submission of complete details/documents.
(2)After expiry of prescribed time limits for an activity, approval for that activity shall be deemed to have been granted.