Indian Boiler Regulations, 1950 (superseded 1 Oct 2026)
Regulation 4C — Recognition of a firm as Competent Authority, Inspecting Authorities, etc.
Text in the DPIIT web edition
Archived copy captured 03 Aug 2022 (Wayback Machine). The text matches the 2019 capture; amendments from 2020 onwards are probably not included. Units as printed.
| Reg. 4 C Recognition of a firm as Competent Authority, Inspecting Authorities etc.: |
| (1) | The Liaison Sub-Committee shall consider the reports and the recommendations of the Evaluation Committee submitted under sub-regulation (3) of regulation 4B and after examining all the aspects of such report, shall either accord recognition to a firm or refuse recognition to such firm. |
| (2) | In case the Liaison Sub-Committee decides to accord recognition to a firm a certificate of recognition in one of the Forms (Form XVI-A to XVI -I) applicable to the area of activity shall be issued by the Secretary, Central Boilers Board and in case the Liaison Sub-Committee decides to refuse recognition, it shall inform the applicant in writing giving reasons therefore. |
Earlier text: the 2008 DIPP web edition
Recognition of a firm as Competent Authority, Inspecting Authorities etc.:
(1)The Liaison Sub-Committee shall consider the reports and the recommendations of the Evaluation Committee submitted under sub-regulation (3) of regulation 4B and after examining all the aspects of such report, shall either accord recognition to a firm or refuse recognition to such firm.
(2)In case the Liaison Sub-Committee decides to accord recognition to a firm a certificate of recognition in one of the Forms (Form XVIA to XVIH) applicable to the area of activity shall be issued by the Secretary, Central Boilers Board and in case the Liaison SubCommittee decides to refuse recognition, it shall inform the applicant in writing giving reasons therefore.
Amendments found
Machine-assisted list from the amending notifications (DPIIT copies; 1990–1998 from scanned Gazette issues on India Code); may be incomplete.
| Date | Notification | Part | Action | What changed (summary) | Web edition |
|---|---|---|---|---|---|
| 1994-07-28 | G.S.R. 402 OCR of scan | (2) | Substituted | Changes the form reference "XVIA to XVIG" to "XVIA to XVIH". Uncertain: OCR reads 'X.'IA to XVIO' and 'XVIA to XVIIH'; read as XVIA to XVIG / XVIA to XVIH. | listed before the capture |
| 1998-11-10 | G.S.R. 221 OCR of scan | (2) | Substituted | Changes 'XVI-A to XVI-H' to 'XVI-A to XVI-I'. Uncertain: Old range garbled ('X\'IA to XVI f{''). | listed before the capture |
| 2010-10-07 | G.S.R. 821(E) | (1) | Amended | Adds the Appraisal Committee alongside the Evaluation Committee. | listed before the capture |
| 2020-09-11 | G.S.R. 551(E) | Substituted | Replaces regulation 4C (recognition of a firm). | check the text |