Indian Boiler Regulations, 1950 (superseded 1 Oct 2026)
Regulation 4B — Scrutiny of applications by the Evaluation Committee
Text in the DPIIT web edition
Archived copy captured 03 Aug 2022 (Wayback Machine). The text matches the 2019 capture; amendments from 2020 onwards are probably not included. Units as printed.
| Reg. 4 B Scrutiny of applications by the Evaluation:- |
| (1) | The Secretary, Central Boilers Board shall send all the applications received under sub-regulation (1) of regulation 4A, along-with replies to the questionnaire under sub-regulation (2) of regulation 4A, to the Evaluation Committee. | ||||
| (2) | The Evaluation Committee shall examine all the applications and replies to the Questionnaire under sub-regulation (1) and
| ||||
| (3) | The Evaluation Committee after satisfying itself that the requirements specified in sub-regulations (1) and (2) are fulfilled, shall submit a report along with its recommendations to the Liaison Sub-Committee. |
Earlier text: the 2008 DIPP web edition
Scrutiny of applications by the Evaluation:-
(1)The Secretary, Central Boilers Board shall send all the applications received under subregulation (1) of regulation 4A, along-with replies to the questionnaire under subregulation (2) of regulation 4A, to the Evaluation Committee.
(2)The Evaluation Committee shall examine all the applications and replies to the Questionnaire under sub-regulation (1) and
(i)where the application is for recognition as Competent Authority or Inspecting Authority, the Evaluation Committee may, (a) call any of the applicants if it considers necessary, to appear before it to give clarification or additional information that may be required by the said Committee; (b) visit any of the applicant firms on a specific request in writing from such firm to evaluate the performance of the said firm:
(ii)where the applicants are for recognition as Well-known Material Testing Laboratory, Well-known Steel Maker, Well-known Foundry or Forge and Well-known tube and pipe maker, the Evaluation Committee shall inspect the laboratory of such Material Testing Laboratory or the factories of such steel makers, foundry or forge and tube or pipe makers, where the testing or manufacturing activities are being carried out in order to evaluate the performance quality of the tests conducted and product manufactured.
(3)The Evaluation Committee after satisfying itself that the requirements specified in subregulations (1) and (2) are fulfilled, shall submit a report along with its recommendations to the Liaison Sub-Committee.
Amendments found
Machine-assisted list from the amending notifications (DPIIT copies; 1990–1998 from scanned Gazette issues on India Code); may be incomplete.
| Date | Notification | Part | Action | What changed (summary) | Web edition |
|---|---|---|---|---|---|
| 1994-07-28 | G.S.R. 402 OCR of scan | (2)(ii) | Substituted | Replaces paragraph (ii) so the Evaluation Committee also inspects laboratories of applicants for recognition as Well-known Material Testing Laboratory. Uncertain: OCR reads 'regulation 4-13'; read as 4-B. | listed before the capture |
| 1998-11-10 | G.S.R. 221 OCR of scan | (2)(ii) | Substituted | Replaces clause (ii) so the Evaluation Committee also inspects Remanent Life Assessment Organisations and other well-known applicants' works. Uncertain: Printed '4-13'; read as 4B. | listed before the capture |
| 2010-10-07 | G.S.R. 821(E) | Substituted | Replaces regulation 4B (scrutiny of applications by the Evaluation or Appraisal Committee). | listed before the capture | |
| 2020-09-11 | G.S.R. 551(E) | (4) | Substituted | Replaces sub-regulation (4) on the committee's report to the Member-Secretary. | check the text |