BETAIndependent engineering reference. Source-text verification is ongoing.Verification ongoing.Verification status →
IBRsourceIndian Boiler Regulations, made clear

Indian Boiler Regulations, 1950 (superseded 1 Oct 2026)

Regulation 266 — General

1 amendment found

Text in the 2008 DIPP web edition

Printed as separate lettered regulations:

Unofficial DIPP web edition (2008) · machine-extracted · not checked against the Gazette

Regulation 266A — General

Regulation 266B — Longitudinal Seams

Regulation 266C — Circumferential Seams

Regulation 266D

Regulation 266I — Removal of Defects

Regulation 266E — Examination before Re-welding

Regulation 266F — Process used for Repairs

Regulation 266G — Radiographical Examination after Repairs

Regulation 266H — Specimen Representing Repairs

Amendments found

Machine-assisted list from the amending notifications (DPIIT copies; 1990–1998 from scanned Gazette issues on India Code); may be incomplete.

DateNotificationPartActionWhat changed (summary)
2005-01-19G.S.R. 32(g)SubstitutedReplaces clause (g) requiring radiographic or radioscopic examination of repaired areas.