Indian Boiler Regulations, 1950 (superseded 1 Oct 2026)
Regulation 249 — Constructional details and preparation for welding
Text in the DPIIT web edition
Archived copy captured 03 Aug 2022 (Wayback Machine); the same page also prints regulations 246, 247, 248. The text matches the 2019 capture; amendments from 2020 onwards are probably not included. Units as printed.
|
| ||||||||
Reg. 247
Reg. 248
Reg. 249
| ||||||||
Earlier text: the 2008 DIPP web edition
Constructional details and preparation for welding
The manufacturer shall supply the Inspecting Authority with a fully dimensioned sectional drawing showing in full details the construction of the drum(s) for approval before putting the work in hand.
Fully dimensioned drawings of the proposed welds preparations of the main seams drawn to a scale which clearly shows all the relevant details shall be furnished.
Sketches showing details of the welds preparations for the attachment of the stand pipes, branch pipes and seatings and their locations relative to the longitudinal and circumferential seams and to other openings shall be furnished.