BETAIndependent engineering reference. Source-text verification is ongoing.Verification ongoing.Verification status →
IBRsourceIndian Boiler Regulations, made clear

Indian Boiler Regulations, 1950 (superseded 1 Oct 2026)

Regulation 519I

Unofficial DPIIT web edition · not verified0 amendments found

Text in the DPIIT web edition

Archived copy captured 03 Aug 2022 (Wayback Machine); the same page also prints regulations 519J, 519K. The text matches the 2019 capture; amendments from 2020 onwards are probably not included. Units as printed.

Unofficial DPIIT web edition · archived 2022 · not checked against the Gazette

Reg. 519 I, Reg. 519 J, Reg. 519 K
STANDARD CONDITIONS FOR THE DESIGN AND CONSTRUCTION OF ECONOMIZER, FEED PIPES, FEED HEATERS AND OTHER SIMILAR VESSELS

VALVES AND MOUNTINGS

(j) Hydraulic Test
All valves and mountings shall withstand satisfactorily a hydraulic test to the same pressure as will be applied to the economiser during its registration.

NOTE:- The working pressure shall be the highest pressure at which the economiser relief are to be set.


Reg. 519
J
STANDARD CONDITIONS FOR THE DESIGN AND CONSTRUCTION OF ECONOMISER, FEED PIPES, FEED HEATERS AND OTHER SIMILAR VESSELS

VALVES AND MOUNTINGS

(j) Feed Line
Alternative means of feeding the boiler other than through the economiser shall be provided.

Reg. 519 K
STANDARD CONDITIONS FOR THE DESIGN AND CONSTRUCTION OF ECONOMIZER, FEED PIPES, FEED HEATERS AND OTHER SIMILAR VESSELS

VALVES AND MOUNTINGS

(k) Non-return valve
A valve shall be provided in the hot feed line between the economiser and the boiler to prevent the discharge of steam or water from the boiler into the economiser.
Earlier text: the 2008 DIPP web edition

STANDARD CONDITIONS FOR THE DESIGN AND CONSTRUCTION OF ECONOMIZER, FEED PIPES, FEED HEATERS AND OTHER SIMILAR VESSELS

VALVES AND MOUNTINGS

(j)Hydraulic Test

All valves and mountings shall withstand satisfactorily a hydraulic test to the same pressure as will be applied to the economiser during its registration.

NOTE:- The working pressure shall be the highest pressure at which the economiser relief are to be set.