Regulation 395 — Submission of plans of steam-pipes

Unofficial DPIIT web edition · not verified4 amendments found

Text in the DPIIT web edition

Archived copy captured 03 Aug 2022 (Wayback Machine); the same page also prints regulation 395A. The text matches the 2019 capture; amendments from 2020 onwards are probably not included. Units as printed.

Unofficial DPIIT web edition · archived 2022 · not checked against the Gazette

Reg. 395, Reg. 395 A

Submission of plans of steam-pipes

a)

Plans of steam pipes shall be submitted with the prescribed fee to the Chief Inspector before construction or at the time of registration of the boiler for his decision whether the pipes and their arrangement comply with the Regulations.
b)
(i) The fees for examination of plans and the particulars of materials, design and construction of steam pipes before the commencement of manufacture of the steam pipes shall be at the rate of Rs. 30/- for 30 meters of piping or part thereof, subject to a minimum of Rs.50/-, inclusive of all fittings excepting the fittings like de-superheaters, steam receivers, feed heaters and separately fired superheaters. For any fittings like de-superheaters, steam receivers, separators and flanges, the fee shall be Rs.150.00 for each category of such identical fittings.
ii) The fees for examination of lay out plans of steam pipes shall be Rs.20/- per 30 metres of piping or part thereof, subject to a minimum of Rs.50/-, inclusive of all fittings, except fittings like de-superheaters steam receivers, feed heaters and separately fired superheaters. For any fittings like de-superheaters, steam receivers and separators, the fee shall be Rs.150.00 for each such fittings.


Reg. 395 A

Inspection fee for boilers and parts thereof constructed in India

1)

The inspection fee for boilers shall be calculated on the following basis:

(i) at four times the registration fee for a boiler of riveted construction.
ii) at four times the registration fee for a boiler of welded construction.
2) Fees for inspections of boiler scantlings shall be charged as under:-

(i) upto 10 square feet (0.929 sq. meter) of outside surface - nil.
ii) above 10 square feet (0.929 sq. meter) of outside surface – one half of the registration fee of the boiler for which the part is intended.
3) For inspection of tubes and pipes, the fees shall be charged at the rate of Rs.150/- per metric tonne or a fraction thereof.
4) Fees for inspection of boiler at the site of construction shall be charged at the rate of four times the registration fee.”.
5) For inspection of forged pipe fittings, the fees shall be charged at the rate specified for forged and cast flanges under clause (1), of sub-regulation (2) of regulation 395 C.
6) For inspection of pipe fittings other than forged pipe fittings, the fees shall be charged as under:-

(a) Upto and including 50mm, for 100 kg. or a fraction thereof Rs. 50/-
(b) Over 50 mm and upto and including 100 mm for 450 kg. or fraction thereof. Rs. 250/-
c) Over 100 mm for 900 kg. or a fraction thereof. Rs. 500/-
Earlier text: the 2008 DIPP web edition

Submission of plans of steam-pipes

a)Plans of steam pipes shall be submitted with the prescribed fee to the Chief Inspector before construction or at the time of registration of the boiler for his decision whether the pipes and their arrangement comply with the Regulations.

b)

(i)The fees for examination of plans and the particulars of materials, design and construction of steam pipes before the commencement of manufacture of the steam pipes shall be at the rate of Rs. 30/- for 30 meters of piping or part thereof, subject to a minimum of Rs.50/-, inclusive of all fittings excepting the fittings like de-superheaters, steam receivers, feed heaters and separately fired superheaters. For any fittings like de-superheaters, steam receivers, separators and flanges, the fee shall be Rs.150.00 for each category of such identical fittings.

ii)The fees for examination of lay out plans of steam pipes shall be Rs.20/- per 30 metres of piping or part thereof, subject to a minimum of Rs.50/-, inclusive of all fittings, except fittings like de-superheaters steam receivers, feed heaters and separately fired superheaters. For any fittings like de-superheaters, steam receivers and separators, the fee shall be Rs.150.00 for each such fittings.

Amendments found

Machine-assisted list from the amending notifications (DPIIT copies; 1990–1998 from scanned Gazette issues on India Code); may be incomplete.

DateNotificationPartActionWhat changed (summary)Web edition
2006-11-08G.S.R. 280(b)SubstitutedReplaces clause (b) on fees for examination of steam pipe plans.listed before the capture
2010-10-07G.S.R. 821(E)(a)AmendedSplits submission between the Inspecting Authority before construction and the Chief Inspector at registration.listed before the capture
2015-08-26G.S.R. 664(E)SubstitutedReplaces regulation 395 (submission of plans of steam pipes).listed before the capture
2020-09-11G.S.R. 551(E)(b)(i), (ii)AmendedChanges the fees from Rs 5,000 and Rs 1,000 to Rs. 500 each.check the text