Indian Boiler Regulations, 1950 (superseded 1 Oct 2026)
Regulation 267B — Heat Treatment
Text in the DPIIT web edition
Archived copy captured 03 Aug 2022 (Wayback Machine); the same page also prints regulations 267A, 267C, 267D. The text matches the 2019 capture; amendments from 2020 onwards are probably not included. Units as printed.
|
| |||||||||||||||||||||||||||||||||
Reg. 267 b
Reg. 267 c
Reg. 267 d
| |||||||||||||||||||||||||||||||||
Earlier text: the 2008 DIPP web edition
Heat Treatment
Where the shell is subjected to a primary stress relieving treatment identical to the final heat treatment to be given to the drum, the test plates may be placed inside the shell during the primary treatment and thereafter cut up and tested without waiting for the final treatment of the drum.